š Overview
On a job site, almost nothing happens on its own. Cabinets wait for drywall, drywall waits for inspections, and inspections wait for rough-ins. When one item slips a few days and nobody moves the work behind it, the schedule says the tile crew starts Monday while the room still has open walls.
Dependencies link schedule items so that the work after an item moves when that item moves or runs long. You draw a link by dragging from one bar to another, or pick it in the item panel. Structur then keeps the sequence for you.
A baseline is a saved copy of your plan. Once it's set, each bar has a grey shadow of its original dates underneath, and the +/- column shows how many days each item has slipped. It's how you show a client, or yourself, where the schedule moved and by how much.
š Understanding Dependencies and Baseline
ā” What It Does
Dependencies and baseline allow you and your team to:
Link items in sequence -- by dragging between bars or picking Predecessors and Successors
Move the work that follows -- when an item runs long or is moved later, its successors move by the same number of days
Save the original plan -- with Set Baseline
See slipped dates at a glance -- grey shadow bars show the planned dates under each bar
Count days of slip -- the +/- column shows how far each item is past its baseline
š When to Use It
Dependencies and baseline are most valuable when you want to:
Keep trades in the right order without re-dating every item by hand
See which items move when one runs long
Lock in the plan you agreed with your client before work starts
Show how far the job has moved from the original plan
š Step-by-Step Instructions
1. Link Two Items on the Chart
Hover the first item's bar. A dot appears at each end.
Drag from the dot at the end of the bar onto the bar of the item that comes next
A dashed line with an arrow joins the two items
Click Save Changes at the top right
The first item is the predecessor, the second is its successor. The footer at the bottom of the chart counts the items and dependencies on the schedule, for example "2 items Ā· 1 dependencies".
Note: Adding a link doesn't move the successor, even when the two items overlap. Drag the successor to where it should start.
2. Link Items from the Item Panel
Click an item's name to open its panel
Under DEPENDENCIES, pick items in Predecessors or Successors
Click Save
Click Save Changes at the top right
Linked items show as chips. Click the x on a chip to remove that link.
3. How Successors Move
Once items are linked:
Extend a predecessor's end date and its successors move later by the same number of days
Drag a whole predecessor later and its successors move with it
Shorten a predecessor and its successors stay where they are
So the schedule pushes work back when something runs long, but shortening an item doesn't pull the work after it forward. If an item finishes early, drag its successors earlier yourself.
4. Remove a Link
Hover the dashed line between two items. It turns orange.
Click the red trash icon
Click Save Changes at the top right
The link is removed without a confirmation.
5. Set a Baseline
When the schedule is final and agreed, click Set Baseline in the toolbar.
Any unsaved changes are saved first, then the baseline is set straight away. The toolbar shows Baseline Set, the button changes to Clear Baseline, and the footer shows "Baseline active". Each bar now has a grey shadow bar underneath with its baseline dates.
6. Track Slipped Days
Click Toggle columns and turn on +/-
Move an item past its baseline dates
The item shows a red day count, such as +2d, under its shadow bar and in the +/- column. An item that finishes ahead of its baseline shows a green count, such as -2d. Items still on their baseline show 0.
7. Clear the Baseline
Click Clear Baseline
Click Clear to confirm
Important: Clearing the baseline removes every baseline date and slip count on the schedule, and it can't be undone. If you set a new baseline afterwards, it uses the schedule's current dates, not your original plan.
ā Best Practices
Link items as you build the schedule -- it's quicker than going back later, and a late item then pushes the right work back.
Check successors when an item finishes early -- shortening an item doesn't move its successors earlier, so the schedule can show idle days that aren't real.
Set the baseline once the client has agreed the plan -- the slip you track afterwards then measures against the dates you committed to.
Turn on the +/- column for progress meetings -- it shows which items slipped and by how much without comparing dates by hand.
Don't clear a baseline to tidy the chart -- the original plan is gone for good once you do.
Link in one direction only -- a link from a later item back to an earlier one creates a loop that stops item saves.
ā Common Questions
Q: Do linked items move when the earlier item moves?
A: Yes, when it moves later. If you extend an item or drag it later, its successors move by the same number of days. If you shorten an item, its successors stay put, so drag them earlier yourself.
Q: Do I need a baseline before I can link items?
A: No. Links and the baseline are separate. You can link items at any time, with or without a baseline.
Q: Why does saving an item say "Failed to update schedule item"?
A: Currently, the chart lets you create a circular link, for example A to B and then B back to A. After that, saving the item from its panel fails, and the loop doesn't show in the panel. To fix it, hover the link that points back to the earlier item, click the trash icon, and click Save Changes. Panel saves then work again.
Q: What does Set Baseline do?
A: It saves the current dates of every item as the plan. A grey shadow bar shows those dates under each bar, and the +/- column shows how far each item has moved past them.
Q: Is the baseline copied when I duplicate a schedule or use a template?
A: No. Duplicate and templates copy the items, groups and links, but not the baseline. Set a new baseline on the new schedule.
ā ļø Common Mistakes to Avoid
ā Don't | ā Do |
Draw links and leave without saving | Click Save Changes after adding or removing links |
Link a later item back to an earlier one | Link in one direction only, from earlier work to later work |
Expect successors to move earlier when an item finishes early | Drag the successors earlier yourself |
Set the baseline while the plan is still changing | Set it once the client has agreed the schedule |
Clear the baseline to tidy up the chart | Keep the baseline for the life of the job so slip is always measured against the original plan |
