š Overview
Three days of rain, a client who changes the tile after it's ordered, rot behind a wall nobody could have seen. These delays aren't your fault, and most contracts allow extra time for them. But at the end of the job, when the client asks why it finished two weeks late, a vague memory of "that wet week in March" won't settle the conversation.
Permitted Delays lets you record each excusable delay on the schedule it affects, as it happens. You note the reason, what happened, the dates, how many days it adds and which items it affects. The records stay together on the schedule, ready when you need to explain the finish date.
A permitted delay is a record, not a reschedule. It doesn't move any dates, so you still drag the affected items yourself.
š Understanding Permitted Delays
ā” What It Does
Permitted Delays allows you and your team to:
Record an excusable delay -- weather, a client-requested change, an unforeseen issue or another reason
Note the dates and the impact -- the delay's start and end dates and the days it adds to the schedule
Tie the delay to the items it affects -- by ticking the impacted schedule items
Keep every delay in one list -- on the schedule, with edit and delete from each record
š When to Use It
Permitted Delays is most valuable when you want to:
Back up a request for more time with a dated record
Explain a late finish to a client with specifics
Separate delays you're entitled to from delays your team caused
Keep a running log of weather days on a job
š Step-by-Step Instructions
1. Open Permitted Delays
Open the schedule
Click Permitted Delays in the header
A drawer opens on the right with the delays recorded on this schedule. If there are none yet, it says "No permitted delays recorded yet".
2. Record a Delay
Click Add Permitted Delay
Choose a Reason: Weather event, Client-requested change, Unforeseen issue or Other
Write a Description of what happened
Enter the Start Date and End Date
Enter the Schedule impact (days)
Under Impacted schedule items, tick the items the delay affects
Click Save
You'll see "Permitted delay recorded". The delay shows in the list with its reason, dates, days added, description and impacted items.
Note: Save stays greyed out until both dates are filled in, and the End Date can't be before the Start Date. The Description is optional, but a delay without one is hard to defend later. Schedule impact (days) isn't worked out from the dates, so enter it yourself.
3. Move the Affected Items
Recording a delay doesn't change any dates, and the delay doesn't show on the chart. Drag the affected items to their new dates, then click Save Changes at the top right. The button appears once you have unsaved changes.
If the items are linked, moving the first one moves the work after it. See Schedule Dependencies and Baseline.
4. Edit or Delete a Delay
Open the three-dot menu on a delay:
Edit opens Edit Permitted Delay with the same fields. Change them and click Save.
Delete asks "Delete this permitted delay?" and warns that it can't be undone. Click Delete to confirm.
Important: A deleted delay can't be recovered. If the delay might matter in a dispute later, edit it instead of deleting it.
ā Best Practices
Record delays the day they happen -- the details are freshest then, and a record made at the time carries more weight than one made at the end of the job.
Write a specific description -- "Site closed, 2 in. of rain, excavation flooded" holds up better than "weather".
Tick every impacted item -- it shows exactly which work the delay held up.
Move the affected items yourself -- the delay record doesn't reschedule anything, so the chart stays wrong until you drag the items.
ā Common Questions
Q: I recorded a delay and ticked the items, but nothing moved. Why?
A: A permitted delay is a record, not a reschedule. Drag the affected items to their new dates and click Save Changes.
Q: Is Schedule impact worked out from the start and end dates?
A: No. Enter the number of days the delay adds to the schedule yourself. It can differ from the number of days between the dates.
Q: Can my client see permitted delays?
A: Delays don't show on the chart or on the read-only page you share with Copy Link. To show a client the record, walk them through the Permitted Delays list or send them the details yourself.
Q: Is this the same as the delays on a daily log?
A: No. The DELAYS field on a daily log is a note in that day's log. A permitted delay is a record on the schedule, with a reason, dates, days of impact and the items it affects. For an excusable delay, note it in the day's log and record it as a permitted delay too.
ā ļø Common Mistakes to Avoid
ā Don't | ā Do |
Expect a recorded delay to move your items | Drag the affected items yourself and click Save Changes |
Leave Schedule impact at 0 | Enter the number of days the delay adds |
Write "weather" and nothing else | Describe what happened, what was affected, and why work stopped |
Wait until the end of the job to record delays | Record each delay as it happens |
Delete a delay to fix a typo | Use Edit and keep the record |