đ Overview
A job runs on its sequence. The framer can't start until the foundation is poured, the drywall crew can't start until rough-ins pass, and one slipped date pushes everything behind it. When that plan lives in a spreadsheet or on a whiteboard in the trailer, nobody sees the knock-on effect until a crew shows up to a site that isn't ready.
Schedules gives every lead and project its own Gantt chart. You list the work as items, group it by phase, drag bars to set dates, and link items so that when one runs long, the work after it moves too. A job can hold as many schedules as you need, and you can start each one from scratch or from a template you've saved.
Schedules also covers what happens around the chart. You can track progress, compare the plan to a saved baseline, record permitted delays, and share a read-only link with your client or crew. Those have their own articles: Schedule Dependencies and Baseline, Permitted Delays, Share a Schedule and All Schedules View.
đ Understanding Schedules
⥠What It Does
Schedules allows you and your team to:
Build a Gantt schedule on any lead or project -- and keep several schedules on the same job
Start from a template -- pick a new start date and every item moves with it, keeping its length and spacing
Organize items into groups -- by phase, trade or area, each with its own color
Drag bars to change dates -- move a whole item or stretch its end date
Add detail to each item -- assignees, vendors, progress, subtasks, notes, attachments and linked tasks
Switch between Day, Week and Month -- and choose which columns show beside the chart
Reuse your best schedules -- duplicate a schedule or save it as a template
đ When to Use It
Schedules is most valuable when you want to:
Plan a job's sequence before work starts, even while it's still a lead
See how one late item affects everything after it
Give your team one place to check who's on site and when
Start each new job from a proven schedule instead of a blank page
Track how far along each item is
đ Step-by-Step Instructions
1. Open Schedules
Open a lead or project
Click Schedules in the module bar along the top (under Project Management)
The list shows every schedule on the job, with cards for In Progress, Delayed and Complete. Use the tabs (All, Not Started, In Progress, Complete, Delayed), Search schedules..., and List or Grid to find one. The list columns are Number, Title, Items, Starts, Ends, Progress, Status and Client Visibility. Click Open to open a schedule.
At the top right are Export (Export PDF or Export CSV), Manage Templates and New Schedule. On a narrower screen, Export and Manage Templates sit under Actions.
Note: PROGRESS on the Schedules list is the share of items that are complete (set to 100%), not an average of item progress. A schedule with two items, one at 100% and one at 65%, shows 50%. A schedule where no item has reached 100% shows 0%. Open the schedule to see each item's own progress. STATUS updates on its own as the schedule moves through Not Started, In Progress and Delayed.
Note: To see schedules from several jobs at once, open the lead or project name at the top of the page, tick the jobs you want ("Tick boxes to pick several") and click Show 2 Selected (the number matches what you ticked). With nothing ticked, the button shows all of them instead, such as Show All Projects on the Projects tab. See All Schedules View.
2. Create a Schedule from Scratch
Click New Schedule
Click Start From Scratch
Enter a Name. It starts as the job's name.
Choose a Default Progress Bar Color for new items
Check Select a project. It lists your leads and projects.
Add a Description if you want one
Click Create
The new schedule opens straight away.
3. Create a Schedule from a Template
Click New Schedule
Click Choose a Template
Pick a template under Select Template
Choose a Start date
Check the Name, Default Progress Bar Color, Select a project and Description
Click Create
Every item moves to the new start date. Each item keeps its length and its gap from the items around it, and groups, progress and links come across too. A baseline isn't copied.
Note: Templates are the ones your company has saved. Structur doesn't come with ready-made templates. To save one, see step 11.
4. Find Your Way Around a Schedule
The header has Show Left Column, Duplicate, Manage Templates, Copy Link, Download, Preview, Permitted Delays and Settings (or they sit under Actions on a narrower screen). Download is a single option, with no choice of format. Preview opens the schedule on its own page in a new browser tab.
Below it, the toolbar shows the schedule's start and end dates and item count, with Set Baseline, Undo, Zoom out, Zoom in, Day, Week, Month and Toggle columns.
The chart opens at the schedule's own start date, not today. A red line marks today.
Show Left Column hides or shows the table to the left of the chart
Toggle columns adds Days, +/-, Assignees and Vendors to Start, End and %
Weekends show as grey columns. Durations count calendar days, weekends included.
Note: Column choices reset when you reload the page.
5. Add Items
Click New Schedule Item at the bottom of the schedule
Type the item's name in the row that says Type schedule item...
Press Enter
A new blank row appears, ready for the next item. New items are dated today, so drag each bar into place or set its dates in the item panel.
6. Edit an Item
Click an item's name to open its panel on the right. You can set:
Name, Group, Start date and End date. Duration (days) is calculated for you and can't be typed in.
Progress, with the slider. The percentage shows beside it.
Color, from the swatches
Assignees (your team) and Vendors (your team and your company's vendors)
Predecessors and Successors under DEPENDENCIES, to link items
Tasks (with + New Task), Attachments (click to upload or drag and drop), SUBTASKS (with Add) and Notes
Fields marked with an asterisk are required. Click Save. Panel changes save straight away, and "Schedule item updated successfully" appears.
Note: SUBTASKS is a checklist inside the item. Items can't be nested under other items. Use groups to organize them.
7. Drag Bars and Save Your Changes
Drag a bar left or right to move both its dates
Drag a bar's right edge to change its end date
Changes you make on the chart wait until you save. An orange Save Changes button appears at the top right with a count of unsaved changes. Click it to save.
This applies to dragging bars, linking items, moving items into groups, and deleting items or groups.
Note: On a narrower screen, Save Changes sits at the bottom of the Actions menu instead, with no count, and nothing else on the chart shows that you have unsaved changes. After you drag a bar, open Actions and click Save Changes.
Note: If you leave with unsaved changes, Structur asks you to confirm. Discard leaves without saving.
8. Organize Items into Groups
Click New Group. A row called "New Group" appears at the top.
Click the group's three-dot menu and click Edit
Enter a Group Name, pick a COLOR, and click Save Changes
Hover an item, grab the drag handle to the left of its name, and drop it on the group row
Click Save Changes at the top
Use the arrow beside a group to collapse or expand it. Each item keeps its own color inside a group.
Important: Deleting a group also deletes every item in it. The confirmation only names the group. Move items out of a group before you delete it. If you delete one by mistake, leave without saving and click Discard.
9. Clone or Delete an Item
Open an item's three-dot menu:
Clone makes a copy of the item with the same dates and no links
Delete asks you to confirm, then removes the item when you click Save Changes
10. Create a Task from an Item
Open the item's panel
Under Tasks, click + New Task
Fill in the task. The Lead / Project and Schedule are already set to this schedule and item.
Click Create Task
The task shows in the item's Tasks list and in Tasks.
11. Duplicate a Schedule or Save It as a Template
Duplicate: click Duplicate in the header, then Duplicate to confirm. A copy named "(Copy)" is created on the same job. It can take a moment to appear. The copy keeps groups, items, links and progress, but not the baseline.
Save as a template:
Click Manage Templates in the schedule's header
Click Convert to Template
Enter a Template Name and click Save
In Manage Templates, you can rename a template with the pencil, turn it on or off with Active, open it with Edit Template, or delete it with the trash icon.
Note: Edit Template opens the template in the normal schedule editor, and nothing on screen says it's a template. Check the title before you make changes.
12. Change Schedule Settings
Click Settings to open Schedule Settings. Change the Name, Default Progress Bar Color, project or Description, then click Save.
Share with client is here too. See Share a Schedule.
13. Delete or Restore a Schedule
Delete a schedule in either of two ways:
On the Schedules list, open the schedule's three-dot menu and click Delete. This deletes it straight away, with no confirmation.
In the schedule, click Settings, then Delete, and confirm
If Enable Restore Mode is on in Settings > Company, the deleted schedule stays in the list struck through, with a Restore button. Click Restore to bring it back.
Important: Delete on the Schedules list doesn't ask first. With Restore Mode off, treat it as permanent. Check you've picked the right row, and check with your admin before deleting a schedule you might need.
â Best Practices
Build a template from your best job -- the next schedule starts on the right dates with the right sequence, instead of from a blank page.
Click Save Changes before you leave -- chart edits aren't saved until you do, and leaving without saving discards them.
Group items by phase -- a long schedule is easier to read and collapse when items sit under Site Work, Framing, Rough-Ins and so on.
Set real dates on new items straight away -- new items start on today's date, so a forgotten item sits in the wrong place on the chart.
Empty a group before deleting it -- the group's items go with it.
Keep Restore Mode on -- a schedule deleted from the list goes with no confirmation, and Restore Mode is how you get it back.
â Common Questions
Q: Can I build a schedule before the job is a project?
A: Yes. Schedules works on leads too. Open the lead and click Schedules, or pick the lead under Select a project when you create the schedule. When the lead becomes a project, the schedule stays with it unchanged.
Q: Do I need to click Save after every change?
A: It depends where you make it. Save in the item panel saves straight away. Changes on the chart, such as dragging bars, linking items or moving items into groups, wait for Save Changes at the top right.
Q: Does the duration skip weekends?
A: No. Durations count calendar days, weekends included. Weekends show as grey columns so you can see them. Currently, there's no working-days setting, so set end dates with weekends in mind.
Q: How do I shift a whole schedule to a new start date?
A: Save the schedule as a template with Manage Templates > Convert to Template. Then create a new schedule with Choose a Template and pick the new Start date. Every item moves and keeps its spacing.
Q: How do I mark an item complete?
A: There's no separate Complete field. Set the item's Progress to 100 % in the item panel and click Save.
Q: What's the difference between a group and subtasks?
A: A group holds several items on the chart, such as every item in a phase. SUBTASKS is a checklist inside one item, and it doesn't show on the chart.
Q: Can I copy a schedule to another project?
A: Duplicate copies it onto the same job. To use it on another job, save it as a template, then create the new schedule from that template and choose the other job under Select a project.
Q: Who gets notified about schedule changes?
A: Schedule alerts are set in Settings > Notifications, under Schedule: Schedule item assigned, Schedule item completed and Schedule item altered.
â ď¸ Common Mistakes to Avoid
â Don't | â Do |
Leave the schedule after dragging bars without saving | Click Save Changes at the top right (or under Actions) before you leave |
Delete a group that still has items in it | Move the items out first, then delete the group |
Click Delete on the Schedules list to "tidy up" without checking | Check the row first. It deletes with no confirmation |
Leave new items on today's date | Drag each item into place or set its dates in the panel |
Rebuild the same schedule for every job | Save a template and create new schedules from it |
Expect durations to skip weekends | Plan end dates with weekends counted |