All Schedules View

Covers seeing schedules across all your leads and projects, switching between All, Leads and Projects, the List, Grid and Gantt views, filtering by project or vendor, including completed projects, and the Schedules widget on Home.

Written by Support

šŸ“‹ Overview

Every schedule can look fine on its own and still clash with the next one. The same framing crew is booked on two jobs the same week, or the plumber you're counting on is already committed across town. You only see it by opening each job's schedule one at a time, and by then someone's already been double-booked.

All Schedules View shows the schedules from all your leads, all your projects, or both, in one place. You can list them, see them as cards, or lay every item from every job on one Gantt chart. Filters narrow it to the projects you pick, or to the schedules a vendor is working on.

Schedules also appear on your Home page, in the Schedules widget, so you can check dates without opening the module.


šŸ” Understanding All Schedules View

⚔ What It Does

All Schedules View allows you and your team to:

  • See every schedule in one list -- across all leads, all projects, or both

  • Switch between List, Grid and Gantt -- the Gantt view puts every item from every job on one chart

  • Filter by project -- tick one or more projects to narrow the list

  • Filter by vendor -- show the schedules that have items assigned to a vendor

  • Include completed projects -- they're hidden until you turn them on

  • Open any schedule -- straight from the list

šŸ“… When to Use It

All Schedules View is most valuable when you want to:

  • Spot clashes between jobs before they happen

  • Check everything a subcontractor is booked on across your jobs

  • Review all active schedules in a weekly production meeting

  • Find a schedule without remembering which job it's on


šŸ“ Step-by-Step Instructions

1. Open All Schedules

  1. Open Schedules on any lead or project

  2. Click the lead or project name at the top of the page

  3. Pick the All, Leads or Projects tab. Each shows a count. Use Search projects... or Filters to narrow the list

  4. Either:

    • Click Show All Projects at the bottom (on the Projects tab) to see every project's schedules, or

    • Tick the jobs you want ("Tick boxes to pick several") and click Show 2 Selected. The number matches how many you ticked. Clear unticks them all

With jobs picked, the top of the page reads SELECTED and the count, such as 2 Projects, followed by their names. The list shows a Lead/Project column so you can tell the jobs apart. With Show All Projects, the column is Project. The list loads 20 schedules at a time and shows "Loading more…" with a count, such as (20 of 23), while it fetches the rest.

Note: On the All tab, leads and projects are listed together, each marked Lead or Project, so you can pick a mix.

Note: You can also get here from Home. In the Schedules widget, click View All, then Go to Schedules.


2. Switch Between List, Grid and Gantt

Click List, Grid or Gantt at the top of the list.

  • List shows each schedule's number, title, items, start and end dates, progress, status and whether it's shared with the client

  • Grid shows each schedule as a card

  • Gantt shows every schedule on one chart, grouped by project, with each project marked in its own color. The toolbar shows the overall start and end dates and the item count, with Day, Week and Month, and the table beside the chart has PROJECT / ITEM, START, END and %

The page remembers the view you used last.


3. Filter by Project or Vendor

  1. Click the filter icon next to the search box

  2. Under PROJECT, tick the projects you want to see

  3. Under VENDOR, tick a vendor to see the schedules they're assigned on

  4. Click Clear all to remove every filter

The filter icon shows a count while a filter is on.

Note: The vendor filter picks whole schedules. A schedule shows if any of its items has that vendor, and the Gantt view then shows all of that schedule's items, not just the vendor's.


4. Include Completed Projects

Completed projects are hidden from this view by default. To see them, open the filter panel and turn on Include completed projects under PROJECTS.


5. See Schedules on Home

On Home, the Schedules widget shows one bar per schedule on a timeline, with Day, Week and Month views. Click View All to see a list of schedules with their dates, and Go to Schedules to open the All Projects schedules page.

Note: The Schedules widget on Home leaves out schedules that haven't started yet. Schedules that have already ended still show. To see a schedule with a future start date, use All Schedules View.


⭐ Best Practices

  • Use the Gantt view in production meetings -- every job's items on one chart makes overlapping crews easy to spot.

  • Filter by vendor before you call a sub -- you'll see every schedule they're on before you ask them to commit to another date.

  • Assign vendors to items -- the vendor filter can only find schedules where the vendor is on an item.

  • Clear filters when you're done -- a forgotten filter makes schedules look missing, and the empty list still says "No schedule added yet".


ā“ Common Questions

Q: Can I see all my projects' schedules on one chart?

A: Yes. Open all schedules for your projects and click Gantt. Every schedule shows on one chart, grouped by project and marked in each project's color.


Q: I filtered by a vendor. Why do I still see items they're not on?

A: The vendor filter picks schedules, not items. Any schedule with that vendor on at least one item is shown in full. Turn on the Vendors column inside the schedule to see which items are theirs.


Q: The list says "No schedule added yet", but I know there are schedules. Why?

A: A filter is probably on. The list shows the same message when no schedules match the filters. Click the filter icon and click Clear all.


Q: Why can't I see schedules for finished jobs?

A: Completed projects are hidden by default. Open the filter panel and turn on Include completed projects.


Q: Can I see schedules for both leads and projects together?

A: Yes. Click the lead or project name at the top of Schedules, open the All tab, tick the leads and projects you want, and click Show with the count, such as Show 2 Selected. The list shows a Lead/Project column so you can tell them apart.


Q: Can I see a few projects' schedules without seeing all of them?

A: Yes. Click the project name at the top of Schedules, tick each project you want, and click Show 2 Selected (the number matches your picks). List, Grid and Gantt all work on the selection.


āš ļø Common Mistakes to Avoid

āŒ Don't

āœ… Do

Open each job's schedule one by one to look for clashes

Use the Gantt view on All Projects

Expect the vendor filter to hide other trades' items

Turn on the Vendors column to see which items are theirs

Forget a filter is on and think schedules are missing

Check the count on the filter icon and click Clear all

Look for finished jobs without changing the filter

Turn on Include completed projects

Read the Gantt view without checking the dates

Open the schedule to confirm an item's dates