Project Manager Workflow

Covers a project manager's jobs in order: your projects, the team and stage on Overview, the Client Portal, schedules, tasks, RFIs, submittals, selections, allowances, daily logs, time, budget, client sharing and completing the job.

Written by Support

šŸ“‹ Overview

A project manager is the person everyone calls. The client wants to know when the cabinets arrive. The architect is waiting on an RFI answer. The sub needs the approved submittal before they order. When those threads run through texts and inboxes, the PM spends the day chasing information instead of running the job.

In Structur, a project manager runs the job from the project's module bar. The Project Management section holds Schedules, Meetings, Tasks, RFIs, Submittals, Selections, Allowances and Warranty, and the field's Daily Logs, Photos and Timesheets. The Client Portal keeps the client informed with the items you choose to share, and Mark Complete closes the job when it's done.

This guide lists those jobs in the order they usually happen on a project and points to the article with the full steps for each.


šŸ” Understanding the Project Manager Workflow

⚔ What It Does

The project manager workflow allows you and your team to:

  • See every project you run in one pipeline

  • Plan the job on a Gantt schedule with dependencies and a baseline

  • Keep questions and approvals moving with RFIs and submittals

  • Get client decisions in writing with selections

  • Track allowances and create change orders from them

  • Keep the client informed through the Client Portal

  • Close the job with Mark Complete

šŸ“… When to Use It

This workflow is most valuable when you want to:

  • Learn what a project manager does in Structur in your first week

  • Run every project the same way

  • Know what's waiting on you, the client or a vendor

  • Give the client one place to follow the job


šŸ“ Step-by-Step Instructions

1. Find Your Projects

Click Projects in the left sidebar and pick My Projects in the scope dropdown. The Dashboard shows a Projects table with the PM and Super for each job.

See Projects Pipeline.


2. Check the Team and Stage on Overview

Open the project. On Overview, click Edit in Project Details to check Stage, the client and the address, then click Save Changes. To check Project Manager(s) and Superintendent(s), click Manage Members while editing.

See Projects Pipeline.

Note: Depending on their role, teammates may only see the projects they're assigned to in Manage Members. If someone can't find the job, add them there.


3. Invite the Client to the Client Portal

On Overview, click Invite Client in Project Details, then Send Invite. Your client signs in with the email on their client record and sees only what you share.

See Invite a Client and What Clients Can See.


4. Build the Schedule

Click Schedules (under Project Management) and create a schedule from scratch or a template. Add items and groups, drag bars to set dates, and link items so the work after an item moves when it runs long. Set a baseline to track slipped days.

See Schedules and Schedule Dependencies and Baseline. To send it to the client or a vendor, see Share a Schedule.


5. Run Tasks, RFIs and Submittals

  • Tasks -- assign the job's to-dos with due dates. See Tasks

  • RFIs -- send numbered questions to vendors. Ball in Court shows whose turn it is, and Mark as Closed closes an answered RFI. See RFIs

  • Submittals -- send documents out for approval and track each round of revisions. See Submittals

Note: An answered RFI stays Submitted until you close it. Close it once you have what you need.

Note: Currently, you aren't emailed when a vendor answers an RFI. Watch your bell and the BALL IN COURT column so you don't miss an answer. See RFI Emails and Responses.


6. Get Client Decisions with Selections

Build a selection with the options for each finish or material and send it. The client comments, picks options and signs with Sign & Complete Selection in their browser.

See Selections and Send a Selection.

Note: A client's pick doesn't change your budget or allowances. When a choice changes the cost, update the allowance yourself.


7. Track Allowances

Allowance lines from the approved proposal appear on the project's Allowances page. Enter the real cost when you know it, and Structur shows an overage or a credit. Select rows and click New Change Order to create a client change order from them, then check the amounts before you send it.

See Allowances and Change Orders from Allowances.


8. Keep an Eye on the Field and the Money

  • Read the crew's Daily Logs. See Daily Logs

  • Check hours in Timesheets. Labor cost flows into the budget's Labor column. See Timesheets and Track Labor Costs

  • Open Budget under Financial Management to follow costs. For the steps in Budget, Invoices, COs and Subcontracts, see the Financial Management articles in the Help Desk


9. Share with the Client

The Daily Logs, Schedules and Invoices lists have a Client Visibility column that reads Shared or Hidden. Shared files carry a Shared badge. Check the result with the Client Portal button on Overview.

See What Clients Can See and View as Your Client.


10. Mark the Project as Completed

Click Actions in the project's header, then Mark Complete. Check the Completion Date and click Mark Complete. The project moves to Completed Projects.

See Projects Pipeline.


⭐ Best Practices

  • Set the PM and Superintendent on every project -- the Dashboard's Projects table shows both, and blanks mean nobody owns the job.

  • Link schedule items -- when one item runs long, the work after it moves, so the finish date stays honest.

  • Close RFIs once answered -- answered RFIs stay Submitted, and an open list hides the ones that really need you.

  • Update allowances when a selection changes the cost -- selections don't touch the budget, so nothing changes until you record it.

  • Check the Client Portal view before telling the client to look -- it shows exactly what's shared.

  • Complete jobs instead of deleting them -- completed projects keep their history and can be re-opened.


ā“ Common Questions

Q: Why is the project's budget empty?

A: You can't see the budget until a proposal is approved. Check the proposal's status on the Proposals page.


Q: Does a client's selection update the allowance?

A: No. Selections and Allowances are separate. Enter the real cost on the Allowances page yourself. See Selections.


Q: Where is the button to complete the project?

A: In the project's header: click Actions, then Mark Complete. On a wide screen, Mark Complete shows as its own button.


Q: My superintendent can't see the project. Why?

A: If their role has View Only or Collaborate on Projects Pipeline, they only see projects they're assigned to in Manage Members on the project's Overview. Add them under Superintendent(s). See Roles and Permissions.


Q: How do I show the client the schedule?

A: Turn on Share with client for the schedule to put it in their portal, or use Copy Link to send a read-only page. See Share a Schedule.


āš ļø Common Mistakes to Avoid

āŒ Don't

āœ… Do

Leave answered RFIs open

Click Mark as Closed once you have the answer

Expect a client's selection to update the allowance

Enter the real cost on the Allowances page

Tell the client to check the portal without checking it

Open the Client Portal view on Overview first

Move a finished job to the Closeout column and stop

Click Actions, then Mark Complete

Leave the team fields empty

Set Project Manager(s) and Superintendent(s) in Manage Members