Submittals

Covers the Submittals list and All Projects view, the Create New Submittal window, adding recipients, sending new submissions, the recipient menu, Mark as Complete and deleting a submittal.

Written by Support

šŸ“‹ Overview

On most jobs, nothing gets installed until someone signs off on it. The cabinet shop drawings sit in the architect's inbox. The window spec gets approved in a phone call nobody wrote down. The tile arrives, and it's the version from two rounds ago. When submittals live in email threads, the approval you need is always the one you can't find.

Submittals keep every document you send out for approval in one place inside the lead or project. You create the submittal, add the people who review it, and send each round of documents as a numbered submission, so you can see what was sent, when, and to whom.

A submittal can be linked to a Subcontract, which fills in the subcontract's vendor. You can also add other vendors, your client, and any email address.


šŸ” Understanding Submittals

⚔ What It Does

Submittals allow you and your team to:

  • Send documents out for review -- shop drawings, product data, specifications and more, from the lead or project

  • Link a submittal to a subcontract -- the subcontract's vendor fills in

  • Choose reviewers -- vendors, your client with Include Client, and team members or any email address under Additional Recipients

  • Ask for a signature -- with Request Signature, ticked by default for each recipient

  • Track each round -- every revision is a new numbered submission

  • Close it out -- with Mark as Complete once the reviews are in

  • See every submittal across your company -- in the All Projects view

šŸ“… When to Use It

Submittals are most valuable when you want to:

  • Get written approval on materials or drawings before work starts

  • Send a revised version without losing the history of earlier rounds

  • See which submittals are still open on a project


šŸ“ Step-by-Step Instructions

1. Open Submittals

  1. Open the lead or project

  2. Click Submittals in the module bar (under Project Management)

At the top right are Export and New Submittal. The cards show Needs Revision, In Review and Approved. The tabs are All, In Progress, Complete and Revisit, each with a count. Use Search submittals..., the filter, and List or Grid.

In List, the columns are Number, Title, Status, Ball in Court and Created. Click Open on a row to open a submittal.

Note: Currently, the Approved card counts every Complete submittal, even one that was completed without an approval. Use the Complete tab for an exact count.

To see submittals from every project, click the project name at the top of the page and click Show All Projects. The list adds a Project column. Submittals from completed projects are hidden until you click the filter icon and turn on Include completed projects under PROJECTS.


2. Create a Submittal

  1. Click New Submittal. The Create New Submittal window opens

  2. On the All Projects list, pick the Project first. Inside a project, it's already set

  3. To link a subcontract, pick it under Subcontract. The window says "Vendor is filled from the subcontract"

  4. Enter a Title, and check the Number and the Submittal Manager (it defaults to you)

  5. Pick a Submittal Type

  6. Click Create Submittal

The submittal is created straight away and opens with the status In Progress and submission 001. It has no recipients yet, so add them next (step 4).


3. Manage Submittal Types

The Submittal Type list starts with Document, Product Manual and Specification.

  1. Click Manage Options next to Submittal Type in the create window (or the gear icon next to it when you edit a submittal)

  2. In Manage Submittal Types, type a name under Add New and click Add. Drag a type by its handle to reorder the list

  3. Click Close

Note: The window says these are the options on the dropdown "when creating or updating a submittal". The list is shared by everyone in your company.


4. Add Recipients

  1. Open the submittal and click Edit (top right)

  2. Under RECIPIENTS, click + New Recipient

  3. In Search Vendors, search by name or email, tick one or more vendors, and click Add Recipients. To add a vendor who isn't in Structur yet, click + Add New Vendor

  4. In the table, choose the Primary Contact. Request Signature is ticked for each recipient. Untick it for anyone who only needs to see the submittal

  5. To add your client, turn on Include Client. To add team members or any email address, use Additional Recipients

  6. Click Send Submittal, then Confirm in Confirm Update

You'll see "Submittal updated successfully".

Important: Saving recipients this way doesn't email them. Recipients get an email when you send a new submission (step 5).

On Edit you can also change the Title, Submittal Manager, Submittal Type and Subcontract.


5. Send a Submission

Each round of documents you send for review is a submission.

  1. Open the submittal and click + New Submission

  2. In Create New Submission, write the Description and add Files (drop them in, or click the area)

  3. Click Send

You'll see "Submission created successfully". The submission gets the next number (002, 003 and so on) and becomes the Current Submission. Each recipient gets an email saying a new submission has been created and asking them to review it.

Note: + New Submission is only there while the submittal is In Progress.


6. Work With a Submittal

The top of a submittal has Mark as Complete, Edit, Copy Link, Download and Preview.

  • RECIPIENTS lists each recipient with Ball In Court and Signature. The row's three-dot menu has Set Ball In Court, View As Recipient, Copy Recipient Link and Delete.

  • SUBMISSIONS lists each round, newest on top, with who created it, the ball in court and its status. CURRENT SUBMISSION shows the latest one.

  • ACTIVITY shows when the submittal and each submission were created.

Change the number: click the Submittal # box, type the number you want and click away.


7. Mark a Submittal Complete

When you have the approvals you need, click Mark as Complete (top right). The status changes to Complete.

Important: Mark as Complete happens at once, with no confirmation. Afterwards Edit and Copy Link are greyed out, + New Submission is gone, and there's no button to reopen the submittal. It isn't blocked by missing signatures, so check every recipient's response first.


8. Delete or Restore a Submittal

  1. On the Submittals list, click the row's three-dot menu (Edit or Delete)

  2. Click Delete

You'll see "Submittal deleted successfully". There's no confirmation. If Restore Mode is on in your company, the row stays in the list with Restore in place of Open. Click Restore to bring it back.

Important: If Restore Mode is off in your company, treat Delete as permanent.


⭐ Best Practices

  • Add recipients before you send documents -- a submission goes to the recipients on the submittal when you send it.

  • Put the date you need a response in the description -- submittals have no due date field.

  • Use New Submission for revisions -- a new round keeps the history of what was sent before.

  • Check every response before Mark as Complete -- completing can't be undone and isn't blocked by missing approvals.

  • Keep Request Signature on for approvers -- a signed approval is the record you'll want if there's a dispute later.


ā“ Common Questions

Q: I created a submittal. Did my vendor get an email?

A: No. Creating a submittal and adding recipients with Edit don't send email. Recipients are emailed when you click + New Submission and Send.


Q: What's the difference between a submittal and an RFI?

A: A submittal is a document you send out to be approved, such as shop drawings or product data. An RFI is a question you need answered. Use Submittals for approvals and RFIs for questions.


Q: Can I edit a submittal after it's created?

A: Yes, while it's In Progress. Click Edit, make your changes, then click Send Submittal and Confirm. To send revised files, use + New Submission instead.


Q: How do I revise a completed submittal?

A: A completed submittal can't be reopened or edited. Create a new submittal for the revised documents, and mention the original submittal number in the title or description.


Q: Can I set a due date or reminder?

A: Submittals have no due date or reminder field. Put the date you need a response in the submission description.


Q: How do I delete a submittal?

A: Click the three-dot menu on its row in the Submittals list and click Delete. If Restore Mode is on in your company, you can bring it back with Restore.


āš ļø Common Mistakes to Avoid

āŒ Don't

āœ… Do

Expect creating a submittal to email anyone

Add recipients, then send a + New Submission

Email the client separately for sign-off

Turn on Include Client so they're a recipient on the submittal

Start a new submittal for every revision

Use + New Submission to keep the history together

Mark as Complete before every reviewer has responded

Check each response first, because it can't be undone