Payments

Covers the Payments list, cards, tabs and row menus, payments from a subcontract, a purchase order or the Payments page, vendor payment requests, retainage and releases, Mark Ready for Payment, Mark as Paid, Edit, Void, Delete and Payment Settings.

Written by Support

šŸ“‹ Overview

The payments you haven't recorded are the ones that hurt. A sub's invoice sits in someone's inbox for three weeks, the Budget says the line is fine, and you approve another change before you find out it isn't.

Payments is where you record what you pay your subcontractors, in the Financial Management section of the module bar. Most payments are recorded against a subcontract, so they draw down what's left on it, and you can hold back retainage until the work is done. You can also record a payment against an approved purchase order, or turn a receipt into a payment. Your vendor can also ask to be paid from their subcontract link. You mark the payment paid when the money goes out, and Structur emails your vendor.

Note: Payments used to be called Bills. If you're looking for Bills, it's this page.


šŸ” Understanding Payments

⚔ What It Does

Payments allows you and your team to:

  • Record what you owe a vendor -- per line on their subcontract or purchase order

  • Receive payment requests -- your vendor asks to be paid from their subcontract link

  • Hold back retainage -- and release it on a later payment

  • Track each payment's status -- Draft, Payment Requested, Ready to Pay, Paid or Voided

  • Record payment -- with Mark as Paid, which emails the vendor

  • Undo a payment -- with Void, which keeps it on record but out of the totals

šŸ“… When to Use It

Payments is most valuable when you need to:

  • Get a sub's invoice into Structur the day it arrives

  • See what you owe vendors and what's past due

  • Hold retainage until a sub's work is finished

  • Fix a payment entered by mistake


šŸ“ Step-by-Step Instructions

1. Open Payments

  1. Open the project

  2. Click Payments in the module bar along the top (under Financial Management)

Export, Settings and New Payment are at the top.

  • Cards: Draft, Payment Requested, Awaiting Lien Waiver, Ready to Pay (with how many are past due) and Paid

  • Tabs: All, Draft, Payment Requested, Awaiting Lien Waiver, Ready to Pay, Paid and Voided

  • Columns: Number, Title, Vendor, Related Document (the subcontract or purchase order), Amount, Due Date, Paid and Status

Switch between List and Grid on the right. Export offers Export PDF and Export CSV.


2. Record a Payment from a Subcontract

This is the quickest way to pay a sub.

  1. Open the approved subcontract

  2. Under Payments, click New payment

  3. In Create New Payment, enter the Title. Check the Payment Date and Due Date.

  4. Under Amount per item, enter the Amount Due on each line

  5. Check the Retainage %, and enter a Release Retainage amount if you're paying out retainage you held before

  6. Check Net payment due and click Create Payment

The top of the window shows what's left: Remaining on subcontract, Left to bill and Retainage held. Every line starts with its full amount left to bill, so change it for a partial payment.

The Due Date fills in from the subcontract's Payment terms, for example 11/12/2026 + Net 30 = 12/12/2026. The Retainage % fills in from the subcontract's Retainage %.

For example, $400.00 of work with 10% retainage and a $30.00 release reads "$400.00 allocated - $40.00 retained + $30.00 released", a $390.00 payment. The payment is Ready to Pay.


3. When Your Vendor Requests Payment

Once a subcontract is approved, your vendor can click Request Payment on their subcontract link, enter an amount per line and send it. You'll find it on the subcontract and the Payments page as Payment Requested, with the subcontract's retainage already taken off.

  1. Open the payment

  2. Check the lines, the Payment date and the Due date. If the vendor didn't pick a due date, set one.

  3. Click Mark Ready for Payment

You'll see "Marked ready for payment", and the payment is Ready to Pay.

Note: Mark Ready for Payment needs a Due date. If it's empty, the date picker opens so you can set it.


4. Record a Payment from the Payments Page

  1. On the Payments page, click New Payment

  2. Enter the Title and pick the Vendor. The Number fills in for you.

  3. Check the Payment Date and Due Date, then click Create Payment

  4. The payment opens as a Draft. Under Line Items, click a row and pick lines under Subcontracts or Purchase Orders. Each line shows its total and what's left.

  5. Click Add

  6. Enter the Amount due on each line. Retainage % fills in from the subcontract, and Net due and Net payment due update.

  7. Click Mark Ready for Payment

The Due Date fills in from Default due period in Settings. The payment shows on the subcontract's Payments list too.

Note: If the subcontract has Require lien waiver on, adding its lines here shows Lien Waiver Will Be Skipped for Subcontract Items. Click Continue Anyway to add them, or create the payment from the subcontract instead.

Note: Lines come from the vendor's approved subcontracts and purchase orders on this project, so pick the Vendor first. If the vendor has no approved subcontract with money left, the Subcontracts list reads "No approved subcontracts with money left for this vendor." For a one-off cost like an equipment rental, record it in Expenses, or use Convert to Payment on its receipt. See Expenses and Receipts.


5. Know the Statuses

  • Draft -- still being filled in. Doesn't count yet.

  • Payment Requested -- your vendor asked to be paid from their subcontract link. Doesn't count until you mark it ready.

  • Ready to Pay -- approved and waiting for the money to go out.

  • Paid -- payment recorded on the date you marked it.

  • Voided -- kept on record at $0.00 but left out of every total.

On the subcontract or purchase order, Payments to date and Remaining include payments that are Ready to Pay or Paid.

Note: On a payment, the Require lien waiver switch is off and can't be changed, and payments aren't held for a lien waiver. The Awaiting Lien Waiver card and tab stay at 0.


6. Mark a Payment as Paid

  1. Open the Ready to Pay payment and click Mark as Paid, or choose Mark as Paid from its row menu on the subcontract

  2. Mark payment as paid? shows the net amount, for example "$270.00 net due ($300.00 less $30.00 retainage held)". Click Mark as Paid.

It's recorded as paid on today's date. You'll see "Payment marked as paid" and "A confirmation email was sent to the vendor." If the vendor has no email on file, it says "No confirmation email was sent to the vendor." The payment shows Paid with its Paid date.


7. Edit a Payment

Edit is at the top of a Ready to Pay or Paid payment, and in the row menu on the Payments list.

On a paid payment, Edit payment? says it "will move back to Draft so you can make changes, and you will need to mark it as Paid again when you are done." Click Edit Payment to go ahead.


8. Void a Payment

  1. Open the paid payment and click Void, or choose Void payment from its row menu on the subcontract

  2. Void payment? says the payment "will be retained for the audit trail but excluded from totals. This can't be undone." Click Void Payment.

The payment shows Voided and $0.00 on the list. It doesn't count in the subcontract's totals, so the amount can be paid again.


9. Delete a Payment

On the Payments list, open the row menu:

  • Draft -- Edit, Mark Ready for Payment and Delete

  • Ready to Pay -- Edit and Delete

  • Paid -- Edit and Void

  • Voided -- Edit and Delete

Delete asks "Are you sure you want to delete this payment for $X? This action cannot be undone." A deleted payment's amount goes back to the subcontract's Remaining.

Tip: Void rather than delete when in doubt. A voided payment stays on record.


10. Payment Settings

On the Payments page, click Settings:

  • Sync new payments with QuickBooks -- payments are posted to QuickBooks Online

  • Default due period -- days after the payment date when payment is due, for example Net 30. New Payment on the Payments page fills in the Due Date from it.

See QuickBooks Online.


⭐ Best Practices

  • Record payments the day the invoice arrives -- a cost that isn't in Structur is a cost your Budget doesn't show.

  • Record sub payments from the subcontract -- the due date and retainage fill in from it.

  • Change the amount for a partial payment -- lines from the subcontract start at their full amount left to bill.

  • Check vendor requests before you approve them -- set the due date and confirm the amounts, then click Mark Ready for Payment.

  • Mark payments paid when the money goes out -- your vendor gets the confirmation and your totals stay true.

  • Void rather than delete -- a voided payment stays on record.


ā“ Common Questions

Q: Where did Bills go?

A: With the new financials, Bills is now Payments. You record payments against a vendor's subcontract or purchase order.


Q: Does Structur send the money?

A: No. Structur records the payment. You pay your vendor the way you always do, then click Mark as Paid.


Q: Does the vendor know I paid?

A: Yes, if they have an email on file. Mark as Paid emails your vendor a confirmation.


Q: My vendor requested a payment. What do I do?

A: Open it from Payment Requested, check the lines and set a Due date if it's empty, then click Mark Ready for Payment. Mark it paid when the money goes out.


Q: How do I hold back retainage?

A: Set Retainage % on the subcontract. Every payment on it fills in that percentage, and you can change it per line. Release it later with Release Retainage on a new payment from the subcontract.


Q: I voided or deleted a payment. Can I pay that amount again?

A: Yes. Neither counts in the subcontract's totals, so the amount is open again.


Q: Why can't I add lines to my payment?

A: Lines come from the vendor's approved subcontracts and purchase orders on this project. Check that the payment has a Vendor picked in General Details, and that the vendor has an approved subcontract or purchase order here with money left on it.


Q: How do I pay a vendor who doesn't have a subcontract?

A: Create a purchase order for them, approve it, and record the payment from it. For a one-off cost you've already paid, like a rental, use Expenses, or Convert to Payment on the receipt. See Purchase Orders, Expenses and Receipts.


Q: Why does it say the lien waiver will be skipped?

A: The subcontract has Require lien waiver on, and you're adding its lines from the Payments page. Click Continue Anyway, or create the payment from the subcontract.


Q: What's the difference between a payment and an expense?

A: Use a payment when you're paying a vendor against their subcontract or purchase order. Use an Expense for money already spent, like a supply run. See Expenses.


āš ļø Common Mistakes to Avoid

āŒ Don't

āœ… Do

Accept the full remaining amount on a partial payment

Change Amount Due to the work actually done

Mark a vendor request ready without checking it

Check the lines and set the Due date first

Leave a payment Ready to Pay after paying

Mark it paid so your totals match

Delete a payment you might need a record of

Void it so it stays on record

Look for Bills in the module bar

Use Payments