š Overview
On a cost plus job, the client pays for what the work actually costs, plus your fee. That only works if every cost gets captured and billed. Miss a few receipts or a week of crew time, and you've paid for the client's project out of your own margin. Bill a number the client can't trace back, and you lose their trust.
The Cost-plus Invoice bills your actual costs straight from the project. You track costs as they happen in Subcontracts, Expenses and Timesheets, then at each billing cycle you pull them onto the invoice, line by line, add your fee, and send it.
š Understanding Cost Plus Invoicing
ā” What It Does
The Cost-plus Invoice allows you and your team to:
Bill actual costs -- from subcontracts, paid expenses and labor
Bill your fee -- from a fee line on an approved change order
See what's already been billed -- Previously Invoiced and Balance to Finish on every line
Hold and release retainage -- per line
Send it like any invoice -- and record payments as they come in
š When to Use It
Cost plus invoicing is most valuable when you need to:
Bill a remodel or custom job where the scope will change
Run time and materials work
Give a client full visibility into what was spent
Track a job against a guaranteed maximum price
š Step-by-Step Instructions
1. Set Up the Job
Open the project's Overview and click Edit
Set Contract Type to Cost Plus and click Save Changes
You don't need a proposal to bill cost plus. If you do send one, spell out your fee and billing cycle in its terms, for example "15% fee on all costs, billed monthly". See Send a Proposal.
Note: Without an approved proposal, the project's budget starts empty. When you add a cost code from the catalog, Structur asks you to confirm, because the new budget line isn't tied to a signed agreement. Click Confirm.
2. Track Costs as They Happen
Record every cost in its module, on the right cost code:
Subcontracts for your subs. Approve the subcontract so it can be billed. See Subcontracts.
Expenses for money already spent. Click Mark as Paid on each one: only paid expenses can be billed. See Expenses.
Timesheets for crew time. See Track Labor Costs.
Note: Payments you record to a sub don't show up on the invoice by themselves. Bill that work from the subcontract line, for the amount you paid.
3. Create the Cost-plus Invoice
Click Invoices in the module bar (under Financial Management)
Click New Invoice, choose Cost-plus Invoice ("Bill actual costs: expenses, commitments, and labor.") and click Create Invoice
Check the Title, Number, Application period ("Billing window covered by this draw"), Invoice Date and Due Date
Check Previously invoiced, which shows what's already been billed on the project
Click Create Invoice
The invoice opens as a Draft. It can't be saved or sent until the total is above $0.00.
Note: The Application period starts after your last pay application or cost-plus invoice. Change it to the period you're billing.
4. Pull In Your Costs
Under Schedule of Values, click Add Cost Codes
Tick lines from CHANGE ORDERS, LABOR, COMMITMENTS or EXPENSES (and PROPOSALS, if the project has one), or use the search box. Labor shows by date with the person, hours and rate, for example "Field Crew - 9h @ $150.00/h".
Check the Total amount picked and click Add (for example Add 3 Cost Codes)
Costs land under COMMITMENTS, EXPENSES & LABOR, one group per document, for example "Subcontract #48 - Framing", "Expense #11 - Lumber run" or Labor.
Labor lines come in with their full cost in Amount Due.
Subcontract and expense lines come in at $0.00. Enter the Amount Due you're billing, for example what you've paid the sub so far.
A line can't bill more than its cost. If you enter more, Structur limits it to what's left to bill.
5. Check What You're Billing
Change the Amount Due or % on any line, or use the buttons above the table on the lines you tick:
Apply Due % -- a percent of what's left on each line
Bill Remaining -- the full balance on each line
Apply Retainage % and Release Retainage % -- hold back or pay out retainage
Reset Amounts clears every amount on the invoice, after you confirm.
Check the total line: Amount Due + Materials Stored - Retainage + Released = Billed this invoice. Example: $2,000.00 on a subcontract, a $1,000.00 expense and $1,350.00 of labor bill $4,350.00 before your fee.
The Summary shows 1. Total costs completed and stored to date, 2. Retainage, 3. Costs less retainage, 4. Less previous invoices and 5. Amount due, with a Change Order Summary.
6. Add Your Fee
Cost lines come in at cost, and the invoice has no fee setting. Bill your fee from a fee line on a change order instead. Set it up once:
Create a client change order titled for the fee, for example Contractor Fee. In the create window, set Overhead % and Profit % to 0, so the fee isn't marked up. See Change Orders.
Add one line on the cost code you use for your fee, and set its amount to your estimated fee for the whole job, for example 15% of $80,000 in expected costs = $12,000.
Get it approved, or click Approve Manually.
Then on each Cost-plus Invoice:
Click Add Cost Codes, open CHANGE ORDERS and tick your fee line
Enter its Amount Due: your fee on this period's costs. For example, $4,350.00 of costs at 15% = $652.50
On the next invoice, the fee line shows what's left, for example "of $1,500.00, $847.50 left", and Previously Invoiced shows what you've already billed.
Note: A fee line can't bill more than its amount. When the job's costs run past your estimate, approve another fee change order for the extra.
Note: Use the fee line, not the Overhead or Profit rows under it. Those rows only bill markup that's already on the change order's lines.
Note: Bill Remaining bills the full balance on every ticked line, your fee line included. Untick the fee line first, or enter the fee by hand.
7. Send It and Record Payment
Click Submit. In Send to Client, check the subject and message and click Send to Client, or turn Email the client off and click Mark as Sent. The invoice moves to Awaiting Payment.
When the client pays, click Mark as Paid, check the Amount, Payment date and Payment method, and click Record Payment. Paid in full, the invoice moves to Paid.
See Invoices and Pay Apps.
Note: Cost-plus invoices and pay applications go out in the order they were created. A Draft cost-plus invoice left behind blocks the next pay application, and the other way round. Send or delete it first.
ā Best Practices
Agree the fee and billing cycle up front -- write them in the proposal or contract terms.
Mark expenses paid as you go -- unpaid expenses don't show up in Add Cost Codes.
Bill every cycle, even small ones -- costs left for later are the ones that never get billed.
Log labor in Timesheets on the right cost code -- it shows up in Add Cost Codes ready to bill.
Attach backup to the invoice -- receipts under Files help the client approve faster.
Watch Budget Remaining on a guaranteed maximum price job -- it tells you how close you are to the cap.
ā Common Questions
Q: Is there a cost plus invoice?
A: Yes. Click New Invoice and choose Cost-plus Invoice. It bills your actual costs from subcontracts, paid expenses and labor.
Q: Do I need a proposal first?
A: No. Set the project's Contract Type to Cost Plus and start tracking costs. A proposal is still a good place to agree your fee.
Q: Why isn't my expense in Add Cost Codes?
A: Only paid expenses show up. Open the expense and click Mark as Paid.
Q: Why did my subcontract line come in at $0.00?
A: Subcontract and expense lines come in at $0.00 so you choose what to bill. Enter the Amount Due. Labor lines come in at their full cost.
Q: Why can't I save my cost-plus invoice?
A: The total has to be above $0.00. Add a cost with Add Cost Codes and enter an Amount Due.
Q: Does my fee get added automatically?
A: No. Costs come in at cost. Bill your fee from a fee line on an approved client change order. See Add Your Fee above.
Q: An expense I already billed shows up in Add Cost Codes again. Will it bill twice?
A: No. It comes in with its full amount under Previously Invoiced and nothing left to bill. Leave it unticked.
Q: Why can't I send my next pay application?
A: A cost-plus invoice created before it is still a Draft. Send or delete it first.
ā ļø Common Mistakes to Avoid
ā Don't | ā Do |
Bill costs on a client change order and pay app | Use a Cost-plus Invoice |
Leave expenses unpaid in Structur | Click Mark as Paid so they can be billed |
Leave the default application period | Set it to the period you're billing |
Assume your fee is on the invoice | Pull in your fee line and bill this period's fee |
Leave overhead and profit on the fee change order | Set both to 0 when you create it |
Save costs up for the end of the job | Bill them every cycle |