Project Budget

Covers the Budget's summary cards, columns, Detailed and Merged views, Include margins, committed vs spent, comments, and the All Projects budget.

Written by Support

šŸ“‹ Overview

Most jobs don't lose money in one big hit. They lose it a few hundred dollars at a time. A supplier order goes out without anyone checking the line. A supply run lands on the wrong cost code. Labor runs long on framing and nobody sees it until the job is closed out.

The Budget is where you catch that while there's still time to act. It lives inside each project, in the Financial Management section of the module bar, and fills in as soon as a proposal is approved. Every line starts with what you estimated it would cost, then shows what you've committed and spent against it, and what's left.

The Budget doesn't hold numbers of its own. It reads your proposals, change orders, subcontracts, purchase orders, payments, expenses and timesheets. To change a number, change the document behind it.


šŸ” Understanding the Budget

⚔ What It Does

The Budget allows you and your team to:

  • See your cost baseline -- the Original Estimate from each approved proposal

  • Add approved change orders -- they raise the Revised Budget on their own lines

  • Track what you've committed -- approved subcontracts and purchase orders

  • Track what you've spent -- payments, paid expenses and labor

  • See what's left -- Budget Remaining on every line and for the project

  • Create documents from the right line -- expenses, subcontracts, purchase orders, change orders and bid packages

  • Keep the conversation with the number -- comments on each cost code

  • See every project at once -- in the All Projects budget

šŸ“… When to Use It

The Budget is most valuable when you want to:

  • Check costs against the estimate before a line runs over, not after

  • See what an approved change order did to your baseline

  • Check how much is left on a line before you sign a sub or place an order

  • Review all your jobs before a weekly meeting


šŸ“ Step-by-Step Instructions

1. Open the Budget

  1. Open the project

  2. Click Budget in the module bar along the top (under Financial Management)

You can also click Open Budget on a subcontract, purchase order, change order, payment or expense.

Until a proposal is approved, the page shows No budget yet and "Your estimate numbers move into the budget once the client approves the proposal." See Send a Proposal.


2. Read the Summary Cards

Hover the i next to each card for its definition.

  • Revised Budget -- approved proposals plus approved change orders, with the original amount and the change orders shown underneath

  • Total Committed -- approved purchase orders, subcontracts and subcontract change orders, with their share of the budget

  • Total Spent -- payments on purchase orders and subcontracts that are Ready to Pay or Paid, plus paid expenses and labor

  • Budget Remaining -- Revised Budget minus Committed, Expenses and Labor, shown as under or over budget

Note: Total Spent is for information. It doesn't lower Budget Remaining a second time, because the subcontract or purchase order a payment belongs to is already in Committed.


3. Cost vs Sale Price

By default the Budget shows each line at cost, without overhead, profit, taxes or internal markup. Your proposal shows the sale price.

Example: a $2,000.00 line with 10% overhead and 10% compounded profit is $2,420.00 on the proposal. The Budget shows $2,000.00 in Original Estimate.

To see the sale price, turn on Include margins above the table. Overhead, internal markup and profit are then baked into the proposal and change order amounts, so that line shows $2,420.00. Turn it off to go back to cost.

Note: Only roles with Budget Margins access see Include margins and the Internal Markup column. A role set to Access Denied sees cost figures only. Change it in Settings > Permissions, under Financial Management. See Roles and Permissions.


4. Read the Columns

Hover the ? on a column for its definition.

  • Cost Code

  • Original Estimate -- the amount from the approved proposal

  • Approved CO's -- approved client change orders on the line

  • Revised Budget -- Original Estimate + Approved Change Orders

  • Committed -- approved subcontracts + approved purchase orders

  • Expenses -- paid expenses

  • Labor -- labor cost of clocked-out timesheet hours (see Track Labor Costs)

  • Budget Remaining -- Revised Budget - Committed - Expenses - Labor

Two more columns are hidden by default:

  • Internal Markup -- markup added on top of the original estimate (sell price minus cost). It doesn't change with Include margins.

  • Spent -- Payments + Expenses + Labor

The Total Amount row at the bottom adds up every column.


5. Read the Rows

Detailed (the default) groups lines under PROPOSALS, one row per approved proposal, for example "Proposal #0024", with its cost codes underneath. Expand a cost code to see each document on it:

  • Purchase Order or Subcontract -- its amount in Committed, and what's left to pay, for example "$250.00 remaining"

  • Payment -- its amount in Spent

  • Expense -- its amount in Expenses, marked Expensed

  • Labor -- timesheet cost in Labor, marked Logged

Click a document row to open a read-only preview. Click Open in Structur to go to the document.

A client change order on a cost code that isn't in any approved proposal gets its own row under CHANGE ORDERS, for example "Change Order #0014", with its amount in Approved CO's. A change order on a proposal line adds to that line instead.

Costs on a cost code that isn't on any approved proposal or change order collect under UNCATEGORIZED.

Merged shows one row per cost code, with every proposal and change order added together.

Use Search Cost Codes... to find a line, the - in the header to collapse all rows, and Fullscreen for more room.


6. Follow a Cost Through the Budget

On a $1,000.00 line:

  1. A purchase order for $400.00 counts once it's approved. Committed shows $400.00 and Budget Remaining $600.00.

  2. A $150.00 payment on that purchase order adds $150.00 to Total Spent as soon as it's Ready to Pay. Committed and Budget Remaining don't change. The purchase order row shows "$250.00 remaining".

  3. An $80.00 expense adds to Expenses, and Budget Remaining drops to $520.00.

A Draft expense you create yourself doesn't count until you mark it paid. An expense converted from a receipt counts while it's still a Draft. See Expenses and Receipts.

Subcontracts work the same way as purchase orders. A Draft subcontract or purchase order doesn't count.


7. Comment on a Cost Code

  1. Click the comment icon at the right end of a cost code line

  2. Type in Add a comment... and click Post comment

A number on the icon shows how many comments the line has. Notes left on that line in the estimate show here too, marked with the estimate number, for example Estimate #0024. To change or remove your own comment, click its three-dot menu and choose Edit or Delete.


8. Create Documents from the Budget

  • New Item in the top right offers New Subcontract, New Expense and New Change Order

  • The + on a cost code line offers New Expense, New Subcontract, New Purchase Order, New Change Order and New Bid Package

Starting from a line's + brings that line with it. For example, Create New Expense shows it under Pre-selected Cost Code, and the new expense opens with the line already added.

You can also tick one or more lines and use the bar at the bottom to create a Subcontract, Expense or Change Order from them.


9. Choose Your Columns

  • Click the column icon at the right end of the table header to turn columns on or off. Use Compact all columns to tighten them. Drag a column edge to resize it, and double-click it to reset.

  • Click Visibility in the top right to choose columns from Select Visible Columns, including the hidden Internal Markup and Spent. Turn on Default Visibility to use the same columns on every project.

Export in the top right offers Export PDF and Export CSV.


10. See the Budget for All Projects

  1. Click the project name in the breadcrumb at the top

  2. Click Show All Projects at the bottom of the list

The All Projects budget shows the four cards for all your projects together, then one row per project with its Stage, Original Estimate, Approved CO's, Revised Budget, Committed, Expenses, Labor and Budget Remaining.


⭐ Best Practices

  • Get the proposal approved before you start buying -- the Budget waits on an approved proposal.

  • Create costs from the line's + -- the cost lands on the right cost code.

  • Get subcontracts and purchase orders approved promptly -- a Draft doesn't count, so the Budget looks healthier than it is.

  • Read the Budget at cost -- turn on Include margins only when you want the sale price.

  • Check Budget Remaining every week -- a line going negative is far cheaper to fix mid-job than at closeout.

  • Fix numbers at the source -- open the document from the line's preview and correct it there.


ā“ Common Questions

Q: Why doesn't my Budget match my proposal?

A: The Budget shows cost, before overhead and profit. Turn on Include margins to see the sale price.


Q: I don't see Include margins. Why?

A: Your role doesn't have Budget Margins access. Ask your admin to check Settings > Permissions.


Q: Where did Subcontract Balance, Bills and Total Costs go?

A: Approved subcontracts and purchase orders now show in Committed, payments show in Total Spent, and what's left on the line is Budget Remaining.


Q: I added a purchase order. Why didn't Committed change?

A: Only approved purchase orders and subcontracts count. Send it and get it approved, or use Approve Manually.


Q: Why didn't Budget Remaining drop when I paid a vendor?

A: The purchase order or subcontract was already counted in Committed when it was approved. Paying it doesn't use the budget twice. The payment shows in Total Spent.


Q: Why is my expense missing from the Budget?

A: An expense counts once it's Paid. Open it and click Mark as Paid.


Q: Why is a change order in its own section?

A: Its cost code isn't in any approved proposal, so it gets its own row under CHANGE ORDERS.


Q: Do invoices show in the Budget?

A: No. The Budget tracks your costs. What you've billed is on the Invoices page.


āš ļø Common Mistakes to Avoid

āŒ Don't

āœ… Do

Expect the Budget to equal the proposal

Read it at cost, or turn on Include margins

Leave subcontracts and purchase orders in Draft

Get them approved so they count

Read Total Spent as what's left

Read Budget Remaining

Leave expenses in Draft

Mark them paid so they count

Turn on Default Visibility for a one-project change

Leave it off unless you want the layout on every project

Wait until closeout to look at Budget Remaining

Check it weekly while you can still act