š Overview
Changes are where contractors give away the most margin. The owner asks for an extra outlet on site, the crew does it, and the paperwork never catches up. By the time anyone writes it down, the work is done, the price is a guess, and the client doesn't remember agreeing to it.
Change Orders lets you price a change, get it approved, and have it flow into your numbers in one place. You'll find it as COs in the Financial Management section of the module bar. A client change order adds to your client's contract and your Budget. A subcontract change order changes what you owe a sub on a subcontract.
š Understanding Change Orders
ā” What It Does
Change Orders allows you and your team to:
Price a change for your client -- with cost code lines, markup, overhead, profit and tax
Change a subcontract -- add to a subcontract's lines
Send it to your client -- by email, on a schedule, or marked as sent
Get it signed online -- your client approves, declines or requests edits from a link
Record an offline answer -- with Approve Manually or Decline
Update the Budget automatically -- approved client change orders add their cost to the line they change
Start from a template -- with Manage Templates and Save as template
š When to Use It
Change Orders is most valuable when you need to:
Get the client's approval before extra work starts
Bill for added scope on the next pay app
Increase a sub's contract when their scope grows
See which changes are still waiting on a decision
š Step-by-Step Instructions
1. Open Change Orders
Open the project
Click COs in the module bar along the top (under Financial Management)
Export, Manage Templates, Settings and New Change Order are at the top.
Cards: Draft, Edits Requested, Pending Approval and Approved. Each card has a Client line and a Subcontract line, with its own total and count.
Tabs: All, Draft, Pending Approval, Approved, Declined, Edits Requested and Voided
Columns: Number, Title, Type (Client or Subcontract), Total, Status, Created and Approved
A Draft change order's row menu has Edit and Delete.
Manage Templates lists your saved change order templates. To make one, open a change order and click Save as template. Settings holds the defaults for new change orders (Default overhead %, Default profit %, Compound profit calculation, Enable tax collection) and Section Templates. Blank defaults use your company default.
2. Create a Client Change Order
Click New Change Order and choose Client ("Change order issued to the client")
Choose Start From Scratch, or Choose A Template, and click Create Change Order
Enter the Title. The Number is filled in for you.
Check Overhead % and Profit %
Leave Compound profit on top of overhead on or off, and turn on Enable tax collection if the change is taxable
Click Create Change Order
The window has Client and Subcontract at the top if you need to switch. Overhead % and Profit % start from your change order defaults, or your company default in Settings > Company, not from the estimate. See Overhead and Profit.
3. Add the Lines
Under Line Items, click in an empty row and type a cost code or name
Tick lines from BUDGET (your approved proposals' lines, with what's left on each), SAVED ITEMS, CUSTOM CODES or STRUCTUR STANDARD, or click Create Cost Code
Click Add
Enter the Qty, Unit cost and, if you want, a Markup percent for each line
The table shows Cost code, Description, Qty, Unit, Unit cost, Subtotal, Markup, Allowance and Total. Add Cost Codes adds more rows and Add Group adds a group. Below the lines you'll see Overhead, Profit and the Change order total amount.
Example: a $1,000.00 line with 10% markup totals $1,100.00. At 15% overhead and 15% compounded profit, that's Overhead $165.00, Profit $189.75 and a change order total of $1,454.75.
To change the percentages later, click Markup & Tax.
Fill in Scope of Work and Terms & Conditions (Insert Template adds saved text). Files and Internal Notes are further down, and a preview of the document shows on the page.
Click Visibility to choose what prints on the change order, such as Overhead %, Profit %, Cost codes, Unit cost and Subtotal. Your client sees the change order the same way.
A Draft change order has Approve Manually, Open Budget, Copy Link, Download, Preview, Visibility, Save as template and Submit.
4. Send It to Your Client
Click Submit
Check the recipient. It's the project's client.
Leave Email the client on ("The client gets an email with a link to the change order.")
Check the Subject, add any CC and a Message
Under Send time, choose Send now or Schedule. Under Reminder, turn on Send a follow-up email to remind the client if they haven't opened or responded.
Click Send Change Order
You'll see "Change order sent". The client gets the change order PDF and a link to review it, and the change order moves to Pending Approval. Its sections are now read only.
To mark it as sent without an email, turn Email the client off. The window says "The client will not be emailed. The change order will be marked as sent." and the button changes to Mark as Sent. Save Only saves without sending.
5. Approve or Decline It
Your client opens the link and clicks Approve, Decline or Request Edits. To approve, they check their Name and Email, pick a signature (Type, Draw or Upload), and can add Feedback or Attachments. The change order shows Approved.
If the client answers outside Structur, open the change order and click Approve Manually or Decline. Approve Manually asks for the same name, email and signature. The status becomes Approved Manually.
Copy Link in the header gives you the same link the client gets.
6. See Where It Goes
An approved client change order:
Adds its cost to the Budget line it changes, in the Approved CO's and Revised Budget columns. The Budget shows cost, so a $1,454.75 change order built on $1,000.00 of cost adds $1,000.00. Markup, overhead and profit stay out of the Budget.
Shows in the Change Order Summary of your next pay app, and its lines can be billed there
7. Create a Subcontract Change Order
Click New Change Order and choose Subcontract ("Change order issued to a subcontract")
Choose Start From Scratch or Choose A Template
Pick the Subcontract, enter the Title, and click Create Change Order
Under Line Items, pick the line from THIS SUBCONTRACT (the subcontract's own lines) or SAVED ITEMS
Enter the Qty and Unit cost. The Amount and Change order total amount update.
Send it to the vendor with Submit, or record their signature with Approve Manually
Subcontract change orders don't carry markup, overhead or profit. The table shows Cost code, Description, Qty, Unit, Unit cost and Amount, there's no Markup & Tax, and the totals always show Overhead $0.00 and Profit $0.00.
Once it's approved, the subcontract total goes up and so does the Budget's Committed. Example: a $250.00 change order on an $800.00 subcontract makes it $1,050.00.
8. Void an Approved Change Order
Open the change order and click Void
Void Change Order asks "Are you sure you want to void the change order ...? This action cannot be undone." Click Void.
The status becomes Voided and its budget impact is reversed. A voided change order has Edit, which takes it back to Draft so you can fix and resend it.
You can't void a change order that's still in use:
Already billed -- void the invoices that bill it, or remove its amounts from them, first
A subcontract change order with live payments -- you'll see "Change order ... cannot be voided while documents on this subcontract are still live: Payment ... Void it first, then void the change order."
9. Delete a Change Order
On the COs list, open a Draft change order's row menu and choose Delete
Delete Change Order asks "Are you sure you want to delete the change order ...? This action cannot be undone." Click Delete.
It's removed from the list. To take back an approved change order, void it instead.
ā Best Practices
Get the approval before the work starts -- a change order approved after the fact is a negotiation, not a formality.
Check overhead and profit on every new client change order -- they start from your defaults, not from the estimate.
Pick lines from BUDGET where you can -- the cost lands on the line it belongs to.
Use a reminder -- the follow-up email chases the client for you.
ā Common Questions
Q: Where do I set overhead and profit on a change order?
A: When you create a client change order, and afterwards with Markup & Tax. They start from Settings on the COs list, or your company default.
Q: Do subcontract change orders have overhead and profit?
A: No. Markup, overhead and profit belong on client change orders. A subcontract change order changes what you owe the sub.
Q: Can my client approve online?
A: Yes. The email links to the change order, where they can Approve, Decline or Request Edits.
Q: Can I send a change order without emailing my client?
A: Yes. In the send window, turn Email the client off and click Mark as Sent.
Q: Why is my approved change order less in the Budget than on the change order?
A: The Budget shows cost, before markup, overhead and profit.
Q: Why can't I void my change order?
A: It's billed on an invoice, or it's a subcontract change order with a live payment. Void those first.
ā ļø Common Mistakes to Avoid
ā Don't | ā Do |
Assume a new change order copies the estimate's overhead and profit | Check Overhead % and Profit % every time |
Delete an approved change order to undo it | Void it, which reverses its budget impact |
Start extra work on a verbal yes | Send the change order and get it approved first |
