š Overview
Two estimators price the same $10,000 job at 10% overhead and 10% profit. One sends $12,000, the other $12,100. Both did it right, and the client still wants to know why the numbers don't match. On a bigger job, the gap is the difference between winning and losing the bid.
The difference is compound profit. With it on, Structur works out profit on your cost plus overhead, so profit comes out higher than overhead even at the same percentage. With it off, profit is worked out on the base cost only.
You set overhead and profit as percentages, as company defaults in Settings > Company and on each estimate and change order. The Budget shows cost unless you turn on Include margins, so overhead and profit appear on your proposals, change orders and invoices.
š Understanding Overhead and Profit
ā” What It Does
Overhead and profit in Structur allow you and your team to:
Price consistently -- with company default percentages that pre-fill on new documents
Choose how profit is worked out -- on cost plus overhead (compound) or on base cost only
Set them per job -- on each estimate and each change order
Show them on invoices -- as separate overhead and profit rows on pay apps
Keep your Budget at cost -- and add your margins to the view only when you want them
š When to Use It
This is most valuable when you need to:
Explain to a client why overhead and profit are different dollar amounts
Make every estimator price the same way
Check the markup on a change order before it goes out
Reconcile a proposal total against your Budget
š Step-by-Step Instructions
1. Understand the Calculation
Structur works out each estimate in this order:
Subtotal = Qty x Unit Cost
Internal Markup = the line's markup % x Subtotal, giving the line Total
Overhead = Overhead % x the line Totals
Profit depends on the compound toggle:
On: Profit % x (line Totals + Overhead)
Off: Profit % x the Subtotals only
Overhead and profit are always percentages. There's no option to enter them as flat dollar amounts.
2. See the Difference
A $10,000 job with no internal markup, at 10% overhead and 10% profit:
Compound on: Overhead $1,000.00, Profit $1,100.00 (10% of $11,000), Total $12,100.00
Compound off: Overhead $1,000.00, Profit $1,000.00, Total $12,000.00
With compound on and the same percentage for both, profit is always the larger amount, because it includes a share of overhead.
3. Set Your Company Defaults
Go to Settings > Company
Turn on Enable default Overhead and Profit ("Pre-fill these percentages on new estimates, budgets, proposals, and change orders.")
Enter your Overhead and Profit percentages
Turn Compound profit on top of markup and overhead on or off
Click Save Changes
Note: Defaults are company-wide and only pre-fill new documents. Estimates and change orders you've already created keep their own percentages. Change orders can also have their own defaults (see step 5). See Company Settings.
4. Set Them on an Estimate
When you create an estimate, check Overhead %, Profit % and the toggle Compound profit on top of overhead. They start from your company defaults. To change them later, click Settings at the top of the estimate. See Estimates.
5. Set Them on a Change Order
On a Client change order, the Create New Change Order window has Overhead %, Profit %, Compound profit on top of overhead and Enable tax collection.
They don't come from the estimate. They start from the change order defaults in COs > Settings (Default overhead %, Default profit % and Compound profit calculation). A default left blank shows Inherit % and uses your company default from Settings > Company. If Enable default Overhead and Profit is off there too, they start at 0%, so enter the percentages you want for the change.
Example: a $2,000 change at 10% overhead and 10% compounded profit gives Overhead $200.00, Profit $220.00 and a total of $2,420.00.
A Subcontract change order has no overhead, profit or tax. It's priced at cost.
A change order created from Allowances opens the same window as a client change order, with your default percentages filled in. Check Overhead % and Profit % before you create it. See Change Orders.
6. See Where They Show
Proposal -- in the price your client sees
Change orders -- in the client change order's total
Pay applications -- as their own overhead and profit rows under each proposal and change order, while Separate Overhead and Separate Profit are on in the Schedule of Values Columns menu. They start on for a new pay app, unless the approved proposal spreads overhead and profit into its line prices.
Budget -- only when you turn on Include margins above the table. With it off, the Budget shows cost, so a $12,100 proposal shows $10,000. With it on, it shows $12,100. You need the Budget Margins permission to see the toggle.
ā Best Practices
Set company defaults before your team starts pricing -- every new estimate and change order then starts from the same numbers.
Agree on compound profit as a company -- the same percentages give different prices with it on or off, and mixed approaches make bids hard to compare.
Check the percentages on every change order -- they start from your change order or company defaults, or 0% if you don't have one.
Explain compound profit to clients up front -- a line in your terms saves a phone call when profit is higher than overhead.
Compare your Budget to cost, not price -- the gap between the proposal and the Budget is your overhead and profit.
ā Common Questions
Q: Why is my profit higher than my overhead when both are 10%?
A: Compound profit is on. Profit is worked out on your cost plus overhead, so on a $10,000 job, overhead is $1,000 and profit is $1,100.
Q: Can I enter overhead or profit as a dollar amount?
A: No. They're percentages only. To hit a target dollar amount, work out the percentage from your cost.
Q: Why are overhead and profit 0% on my new change order?
A: Change orders start from the defaults in COs > Settings, or your company default in Settings > Company when those are blank. If neither has a percentage, they start at 0%. A subcontract change order never has overhead or profit.
Q: I changed my defaults. Why didn't my estimate update?
A: Defaults only pre-fill new documents. Change the percentages on the estimate itself with Settings.
Q: Why aren't overhead and profit in my Budget?
A: The Budget tracks cost, so you can see what's left to spend. Turn on Include margins above the table to see the amounts with your overhead and profit. If you don't see the toggle, ask your admin for the Budget Margins permission.
Q: Why does my pay app show overhead and profit as separate lines?
A: Separate Overhead and Separate Profit are on in the Schedule of Values Columns menu, so overhead and profit show as their own rows you can bill. They start on unless the approved proposal spreads overhead and profit into its line prices.
ā ļø Common Mistakes to Avoid
ā Don't | ā Do |
Try to enter overhead or profit as a flat amount | Enter percentages, worked out from your cost if you need a target |
Let each estimator choose compound on or off | Set it as a company default and stick to it |
Assume a change order copies the estimate's percentages | Check Overhead % and Profit % on every change order |
Expect existing estimates to change with your defaults | Update them on the estimate itself |
Compare your proposal total to the Budget at cost | Turn on Include margins, or remember the difference is overhead and profit |
