š Overview
An allowance only protects your margin if the difference actually gets billed. When the client's countertop comes in $1,800 over the allowance, that number has to get onto a change order, signed, and into the budget. Done by hand, it's easy to bill the full price instead of the difference, forget a credit you owe the client, or bill the same overage twice.
On the Allowances page you can select one or more allowance rows and create a client change order from them. Structur puts one line on the change order for each row you select and links the rows to it. When the change order is approved, the rows show Complete and the amount shows in the project's Budget.
It works for credits too. A row that came in under its allowance becomes a negative line, so one change order can bill an overage and pass a credit back at the same time.
š Understanding Change Orders from Allowances
ā” What It Does
Creating a change order from allowances allows you and your team to:
Bill several allowances at once -- one change order with a line for each selected row
Pass credits back -- rows under their allowance become negative lines
Skip the retyping -- the cost code and description come over from the allowance
Send it to your client or approve it yourself -- with Submit or Approve Manually
See it in the Budget -- the approved amount shows under APPROVED CO'S
Start over -- void or delete the change order and the rows go back to Pending
š When to Use It
Change orders from allowances are most valuable when you need to:
Bill your client for a finish that came in over its allowance
Credit your client when an allowance came in under
Settle several allowances with one signature
Correct an allowance change order that went out wrong
š Step-by-Step Instructions
1. Enter the Actual Costs
On the Allowances page, enter the real ACTUAL UNIT COST for each row you want to bill, and check its VARIANCE. See Allowances for how actuals and variance work.
Note: Currently, if you change ACTUAL QUANTITY, the change order line can come out different from the VARIANCE. Leave the quantity as it is and change ACTUAL UNIT COST instead.
2. Select the Rows
Tick the checkbox on each row you want to bill. To select every line in a group, tick the group's checkbox. The checkbox in the header selects everything.
Click New Change Order in the page header. It stays greyed out until a row is selected.
To bill a single row, open its Row actions menu and choose New Change Order.
Note: Only Pending rows can be selected. Rows showing a VARIANCE of $0.00 can be selected too, so untick any row with nothing to bill.
3. Create the Change Order
In the Create New Change Order window, type a Title. Issued To is set to Client and can't be changed
Check the Number. It's filled in with the next change order number
Check Overhead %, Profit % and the tax settings. They're filled in from your company's change order defaults, so change them if this change order should be billed differently
Check the allowance rows listed in the window, with the variance for each
Click Create Change Order
Create Change Order stays greyed out until you type a title. When it's done you'll see "Change order created" and Structur opens the new change order. On the Allowances page, the selected rows now show In Progress.
4. Check the Change Order
The new change order opens as soon as it's created. It's a Draft client change order with the title you typed. To find it again later, click COs in the module bar along the top (under Financial Management).
Each selected row is one line. The cost code starts with the proposal number, for example "Proposal #12 09-300 Tile", and the description comes over from the estimate. A credit row comes in as a negative amount.
The change order uses the overhead, profit and tax you set when you created it. Check them against what you agreed with your client, and change them on the change order if needed.
Note: Currently, when ACTUAL QUANTITY was changed on a row, its change order line can differ from the VARIANCE on the Allowances page. Compare every line with the VARIANCE column before you send, and correct the line on the change order if it doesn't match.
5. Send It or Approve It
To send it to your client:
Click Submit
In the Send Change Order window, check the client shown at the top and leave Email the client switched on
Check the Subject, add anyone else under CC (optional), and write a Message if you want one
Click Send Change Order
You'll see "Change order sent". The change order moves to Pending Approval and the allowance rows stay In Progress. If you switch Email the client off, the button reads Mark as Sent: the change order still moves to Pending Approval, but no email goes out.
To record the approval yourself:
Click Approve Manually
In the Approve Change Order window, check the Name and Email (they're filled in with yours)
Pick a signature under Select a signature, or draw your own
Add Feedback if you want, then click Approve
You'll see "Change order approved". The change order shows Approved Manually and the allowance rows change to Complete.
6. See It in the Budget
On the Allowances page, open a Complete row's three-dot menu (View CO, Open Budget, Recent Activity) and click Open Budget, or click Open Budget on the change order.
The approved amount shows under APPROVED CO'S on the proposal's row and on the estimate groups it came from, and REVISED BUDGET updates to match. It isn't listed separately under CHANGE ORDERS.
To get back to the change order from the Allowances page, use View CO in the row menu.
7. Void or Delete to Start Again
If an actual cost changes after the change order is created, the rows stay locked until the change order is gone.
For an approved change order:
Open the change order and click Void
In the Void Change Order window, click Void to confirm
You'll see "Change order voided". The Budget amount is reversed and the rows go back to Pending, ready to edit and select again.
For a Draft change order, open the row menu on the COs list, click Delete and confirm. The rows go back to Pending.
Important: Voiding takes the amount off the Budget. You can reopen a voided change order later with Edit, which takes it back to Draft, but it stays off the Budget until it's approved again. Check you have the right change order before you click Void.
Note: Currently, if you restore a deleted change order, its allowance rows stay Pending, so the same amount could end up on a second change order. Create a new change order from the rows instead of restoring the old one.
ā Best Practices
Settle allowances in batches -- one change order for several rows means one signature from your client instead of several.
Check every line against Variance before you send -- a changed quantity can currently throw off the line amount.
Untick rows with nothing to bill -- a $0.00 row still goes on the change order and locks the row.
Agree on markup with your client first -- the change order picks up your company's default overhead, profit and tax, so check them in the Create New Change Order window.
Give the change order a clear title -- "Kitchen tile allowance" tells your client exactly what they're signing.
Void an approved change order rather than deleting it -- voiding keeps the record, reverses the Budget and puts the rows back to Pending.
ā Common Questions
Q: Does the change order bill the full actual cost or just the difference?
A: Just the difference. Each selected row becomes one line for its variance. Currently, if you changed ACTUAL QUANTITY, check the line against the VARIANCE column before you send.
Q: Can I put several allowances on one change order?
A: Yes. Select all the rows you want, then click New Change Order. Each row becomes its own line.
Q: Can I give my client a credit?
A: Yes. Select a row that came in under its allowance. On its own it makes a negative change order. Mixed with overages, the change order nets them out.
Q: Where do the overhead, profit and tax on the change order come from?
A: They're filled in from your company's change order defaults in the Create New Change Order window. Change Overhead %, Profit % or the tax settings there before you click Create Change Order.
Q: Why can't I select a row?
A: It already has a change order, so it's In Progress or Complete. Void the change order, or delete it while it's a Draft, and the row goes back to Pending.
Q: The real cost changed after I created the change order. What do I do?
A: Void the change order if it's approved, or delete it if it's still a Draft. The row goes back to Pending. Update the actual cost, then create a new change order.
Q: Where does the change order show in the Budget?
A: On the proposal's row, under APPROVED CO'S, once it's approved. It isn't listed separately under CHANGE ORDERS.
Q: How do I tell which allowance a change order came from?
A: Each line's cost code starts with the proposal number, for example "Proposal #12". From the Allowances page, a Complete row's menu has View CO.
ā ļø Common Mistakes to Avoid
ā Don't | ā Do |
Write a separate change order for the full actual cost | Create it from the Allowances page so it carries only the difference |
Send without checking the line amounts | Compare each line with the VARIANCE column first |
Leave $0.00 rows selected | Untick rows with nothing to bill |
Delete a change order, then restore it | Void it and create a new change order from the rows |
Try to edit actuals while a change order is open | Void or delete the change order first, then update the actuals |
