Allowances

Marking estimate lines as allowances, the Allowances page and its cards, entering actual costs, how Variance works, the Pending, In Progress and Complete statuses, the row menu, Export and the All Projects list.

Written by Support

šŸ“‹ Overview

Most jobs are priced before the client has chosen everything. The tile. The light fixtures. The appliances. You put a placeholder number in the estimate and move on. Then the client picks the tile that costs twice as much, and months later nobody remembers what number was in the contract. The difference comes out of your margin, or turns into an awkward conversation at the end of the job.

Allowances keeps track of those placeholder amounts for you. You tick Allowance on the estimate lines that are still to be chosen. Once the client approves the proposal, those lines appear on the project's Allowances page. When you know the real cost, you enter it there, and Structur shows the difference as an overage or a credit.

From there you can turn the difference into a change order: tick the rows and click New Change Order at the top of the page.


šŸ” Understanding Allowances

⚔ What It Does

The Allowances page allows you and your team to:

  • Mark estimate lines as allowances -- with the Allowance checkbox on each line

  • See every allowance in one place -- grouped by proposal, then by estimate group

  • Enter the real cost -- type the actual quantity and unit cost for each line

  • See overages and credits at a glance -- in the Overages, Credits and Net Variance cards

  • Track where each allowance stands -- Pending, In Progress or Complete

  • Bill the difference -- create a change order from one or more rows

  • Look across projects -- with Show All Projects

šŸ“… When to Use It

Allowances are most valuable when you need to:

  • Price a job before the client has picked finishes, fixtures or appliances

  • Show your client exactly where the final cost came in over or under the allowance

  • Keep track of which allowances are settled and which are still open

  • Bill an overage, or pass a credit back, without rebuilding the estimate


šŸ“ Step-by-Step Instructions

1. Mark Lines as Allowances in the Estimate

  1. Open the estimate on the lead or project

  2. Find the line for the item your client still has to choose

  3. Tick the box in the Allowance column. It turns orange.

Ticking Allowance doesn't change the line's price or the estimate totals. Allowance lines carry markup like any other line.

Note: Tick every allowance before the proposal is approved. You can still change the checkbox while the proposal is Pending Approval. Once the proposal is approved, the whole estimate becomes read-only and the Allowance checkbox is greyed out. To change it after that, click New Revision on the estimate. The revision keeps your Allowance ticks and can be edited.


2. Get the Proposal Approved

Allowance lines show in the proposal's pricing table like any other line. There's no allowance label, and none of the pricing options hide them.

The lines appear on the Allowances page once the proposal is Approved, either by your client or with Approve Manually. Until then, the page shows No allowances yet.

Note: If you want your client to know which lines are allowances, say so in the line description, for example "Tile allowance".


3. Open Allowances

  1. Open the lead or project

  2. Click Allowances in the module bar along the top (under Project Management, after Selections)

Note: If you don't see Allowances, it may be hidden. Click Show/Hide Features at the right end of the module bar and turn on Allowances.


4. Read the Page

Three cards sit at the top. Overages adds up every line that came in over its allowance. Credits adds up every line that came in under. Net Variance is the two together.

Rows are grouped by proposal. Each group is labelled with the proposal number and the estimate title, for example "Proposal #0012 - Smith Kitchen Remodel". Under it are the estimate groups and subgroups that hold allowance lines. Groups start collapsed. Click the chevron to open one. Every group shows its own Allowance Total, Actual Total and Variance.

The columns are Cost Code, Description, Original Quantity, Unit, Original Unit Cost, Allowance Total, Actual Quantity, Actual Unit Cost, Actual Total, Variance and Status. You can sort by Status. On a smaller screen, scroll the table sideways.

Allowance Total is the line's cost from the estimate, before markup.

Note: Currently, the Unit column can show Hours on a line that has no unit on the estimate. Check the unit on the estimate if it matters.

Note: Currently, the Net Variance card can drop the minus sign, so a net credit can look like a net overage. Compare Overages and Credits. If Credits is the larger number, the net is a credit.


5. Enter the Actual Cost

Actual Quantity and Actual Unit Cost start as a copy of the original values, so a new row shows a Variance of $0.00 until you change them.

  1. Click the Actual Unit Cost box on the row

  2. Type the real unit cost

  3. Press Tab or click away

There's no Save button. Your change saves as soon as you leave the box.

Note: Currently, when you edit a line inside a subgroup, the totals on the group above it don't update until you reload the page. The line and its subgroup update straight away.

Actual Total is the actual quantity times the actual unit cost. Variance is the actual total minus the allowance total. An overage shows in red and a credit in green. Unit costs are rounded to two decimals.

For example, a tile allowance of 2 rooms at $1,000.00 comes in at $2,300.00 in total. Leave Actual Quantity at 2 and set Actual Unit Cost to $1,150.00. Variance shows $300.00 in red.

Note: Currently, Actual Quantity only takes whole numbers. A quantity of 0.5 shows as 1, and anything you type is saved as a whole number, which can create an overage nobody intended. Leave the quantity as it is and change Actual Unit Cost until Actual Total matches the real cost. This also keeps the change order amount right.


6. Track the Status

Each row shows one of three statuses:

  • Pending (grey) -- no change order yet. You can edit the actuals and select the row.

  • In Progress (yellow) -- a change order has been created from the row. This starts as soon as the change order exists, even while it's still a Draft or waiting for your client.

  • Complete (green) -- the change order has been approved.

While a row is In Progress or Complete, its actuals are locked and its checkbox is greyed out. If the change order is voided or deleted, the row goes back to Pending and you can edit it again. Complete rows still count in the cards.


7. Use the Row Menu

Each row has a Row actions menu on the right.

  • On a Pending row it offers New Change Order (for that row only) and Recent Activity

  • On a Complete row it offers View CO, Open Budget and Recent Activity. Open Budget opens the project's Budget page.

Recent Activity shows who changed the actuals and when a change order was created from the row.


8. Export or See All Projects

Click Export at the top of the page and pick a format.

To look across projects, click the project name in the header and click Show All Projects. You get a list with Project, Client, Description and Created Date. Click Open on a project to go to its Allowances page. There's a matching list for leads.


⭐ Best Practices

  • Tick allowances before the proposal is approved -- once it's approved, the estimate is read-only and you'd need a new revision to add one.

  • Name allowance lines clearly -- the proposal doesn't label allowances, so a description like "Tile allowance" tells your client what the number is.

  • Enter actuals as soon as the real price is known -- the cards only show the overages and credits you've entered.

  • Change the unit cost, not the quantity -- quantities currently save as whole numbers, and changing the quantity can throw off the change order amount.

  • Read Overages and Credits, not just Net Variance -- the two cards show which way the net really goes.

  • Settle the actual before you create the change order -- once a change order exists, the row is locked until you void or delete it.


ā“ Common Questions

Q: I ticked Allowance but nothing shows on the Allowances page. Why?

A: Allowances appear only once the proposal is Approved. Check the proposal's status. If it's approved, reload the Allowances page.


Q: Can I mark a line as an allowance after the proposal is approved?

A: Not on that estimate, because an approved estimate is read-only. Click New Revision on the estimate to make an editable copy. It keeps your Allowance ticks.


Q: Does marking a line as an allowance change its price?

A: No. The line keeps its price, and markup applies to it like any other line.


Q: Will my client see which lines are allowances?

A: Not unless you tell them. On the proposal, allowance lines look like any other line. Put "allowance" in the line description if you want your client to know.


Q: Why does every row show a variance of $0.00?

A: The actual quantity and unit cost start as a copy of the original. The variance changes once you enter the real cost in Actual Unit Cost.


Q: Where do the actual costs come from?

A: You enter them yourself on the Allowances page. Type the real cost once you know it, for example from the supplier's invoice or your client's final choice.


Q: Why can't I edit the actuals or tick a row?

A: A change order has already been created from that row, so it's In Progress or Complete. Void the change order (or delete it while it's a Draft) and the row goes back to Pending.


Q: I voided a proposal. Why are its allowances still listed?

A: Rows from a voided proposal stay on the page under that proposal's group, and they can still be selected. Check the proposal number in the group label before you create a change order.


Q: Who can use Allowances?

A: Access is set in Settings > Permissions. The Allowances row is in the Financial Management group there, even though the module bar shows Allowances under Project Management.


āš ļø Common Mistakes to Avoid

āŒ Don't

āœ… Do

Plan to tick allowances after the client approves

Tick every allowance before the proposal is approved

Type a new number in Actual Quantity

Leave the quantity and change Actual Unit Cost

Read Net Variance on its own

Compare Overages and Credits to see which way the net goes

Expect your client to spot allowances on the proposal

Say "allowance" in the line description

Create a change order before the actual cost is final

Enter the final actual first, since the row locks once a change order exists

Select rows without checking the group label

Check the proposal number, since voided proposals keep their rows