Track Labor Costs

Where hourly rates are set, how labor cost is worked out, picking a Budget cost code in New Entry, the timer and Edit, the Unbudgeted badge, reading labor and Uncategorized in the Budget, moving labor, and QuickBooks.

Written by Support

šŸ“‹ Overview

On most jobs, labor is the number you find out last. Materials have invoices and subs have contracts, but crew hours sit on time cards until payroll. By the time someone works out what the labor actually cost, the framing is done and the overrun is already locked in.

In Structur, every timesheet entry carries an hourly rate, and its labor cost flows into the project's Budget automatically. The cost code on the entry decides where it lands: a line picked from the project's Budget puts the labor on that line, while a code from outside the Budget, or no code, puts it in the Budget's Uncategorized section.

Getting the cost code right is what turns your timesheets into real job costing. This article covers rates, cost codes and how to read labor in the Budget.


šŸ” Understanding Labor Costs

⚔ What It Does

Labor costs in Timesheets allow you and your team to:

  • Set a default hourly rate per user in Settings > Users that fills in on their new entries

  • Work out labor cost automatically from the rate, the hours and the breaks

  • Book labor to a budget line by picking the line from the project's Budget

  • Spot time outside the budget with the Unbudgeted badge

  • See labor by budget line in the Budget's labor column

  • Move labor to the right line by editing an entry's cost code

šŸ“… When to Use It

Tracking labor costs is most valuable when you need to:

  • Compare labor spent against what you estimated while the job is running

  • Find which part of the job is eating the most crew hours

  • Catch time that's been booked outside the budget

  • Keep labor out of Uncategorized so your Budget reports stay clean


šŸ“ Step-by-Step Instructions

1. Set Each User's Hourly Rate

Each user's default rate lives in Settings > Users.

  1. Go to Settings > Users

  2. Open the row menu on the user and click View details

  3. Enter the Hourly Rate

  4. Click Save Changes

You see "Member settings updated successfully." The rate is the person's profile rate. New entries use it unless you type a different Hourly Rate on the Daily or Weekly tab, and the Crew tab always uses it. You can see each entry's rate in the Hourly Rate column of the Timesheets list.

Note: Changing a user's rate doesn't change their existing entries. Entries already saved keep the rate they were saved with. To change an old entry's rate, edit the entry.


2. Understand How Labor Cost Is Worked Out

Labor cost is the entry's hourly rate times its time total, and the time total already has breaks taken out.

For example, an 8:00 AM to 5:00 PM shift with a 30-minute break at $150.00/hr has a time total of 8h 30m and a labor cost of $1,275.00.

A running timer doesn't count yet. The cost reaches the Budget when the person clocks out.


3. Pick a Budget Line in New Entry

In the Create New Time Entry window (Daily, Weekly and Crew tabs), the cost code field opens a Cost codes list.

  1. Click the cost code field (Select cost code)

  2. Look in the BUDGET section. Lines are grouped under the document they come from, such as a proposal, change order or subcontract

  3. Each line shows its budget and what's left, for example "of $1,500.00, $225.00 left". Labor you log on the line counts against what's left

  4. Click the line

You can type a code or name to narrow the list. Below BUDGET are your company's CUSTOM CODES. Each entry takes one cost code.

Note: If your role doesn't have access to the Budget, the BUDGET lines are still listed so you can pick one, but without the budget and "left" amounts.

Note: Currently, some entries can land in Uncategorized in the Budget even when you picked a Budget line. Check Uncategorized after logging time, and move any entry there to the right line with Edit (see step 7).


4. Pick a Budget Line on the Timer or in Edit

Select Cost Code on the running timer and in Edit Timesheet Entry opens the New Cost Code window instead.

  1. Click Select Cost Code

  2. Stay on the Budget tab. Each line shows the document, such as Proposal #0017, then the code and name

  3. Select the line and click Save

The Catalog tab lists Structur Standard and Custom Codes. Every Catalog code carries an Unbudgeted badge.


5. Use a Code Outside the Budget Only When You Mean To

When you pick a code that isn't a Budget line, the Confirm Adding Cost Codes window warns that it creates new budget line items not tied to an executed agreement, which can cause job-costing variances. Click Confirm to go ahead, or Back to selection to pick a Budget line instead.

The saved entry shows a yellow Unbudgeted badge next to its code in the Timesheets list, and its labor goes to the Budget's Uncategorized section.

Note: These codes are useful for work that isn't in the contract yet. If the work belongs to an approved proposal or change order, pick its line from the Budget instead.


6. Read Labor in the Budget

  1. Open the project

  2. Click Budget in the module bar along the top (under Financial Management)

  3. Find the labor column. It's headed Labor

The column shows the labor cost in dollars, not a count of hours.

  • Entries with a Budget line add to that line

  • Entries with a code from outside the Budget, or no cost code, appear in the UNCATEGORIZED section


7. Move Labor to the Right Line

If labor landed in Uncategorized or on the wrong line:

  1. In Timesheets, click Open on the entry, or open the row menu and click Edit

  2. Click the cost code under Select Cost Code and pick the right line on the Budget tab, then click Save

  3. Click Update

The Unbudgeted badge goes away, and the labor moves to the new line in the Budget.


⭐ Best Practices

  • Set hourly rates before your crew starts logging time -- new entries take the profile rate, so setting it first means every entry starts with the right cost.

  • Pick from the Budget by default -- a Budget line puts the labor where it was estimated, and its "left" amount shows how much room remains.

  • Treat the Unbudgeted badge as a flag -- it means the time isn't tied to a signed proposal or approved change order, so check it was meant to be.

  • Check Uncategorized every week -- it's where outside-the-budget and uncoded labor collects, and a quick edit moves it to the right line.

  • Don't record the same labor as an expense -- labor and expenses both count toward the Budget's costs, so the same crew time in both is counted twice.

  • Read the labor column as dollars -- comparing it to hours worked will make every job look wildly off.


ā“ Common Questions

Q: Why is my labor showing under Uncategorized?

A: The entry either has a code from outside the Budget or no cost code. Open the entry, pick its line on the Budget tab, click Save, then Update. The labor moves to that line.


Q: Why does the Labor column show a dollar amount?

A: The labor column in the Budget shows labor cost, not hours. It's each entry's hourly rate times its time total.


Q: What does the Unbudgeted badge mean?

A: The cost code didn't come from a line in the project's Budget. The labor goes to Uncategorized in the Budget instead of a proposal or change order line.


Q: Do breaks lower the labor cost?

A: Yes. Breaks are taken out of the time total, and the labor cost is worked out from the time total.


Q: Where do I set someone's hourly rate?

A: In Settings > Users. Open the row menu on the user, click View details, enter the Hourly Rate and click Save Changes. You can also type a different rate on a single entry on the Daily or Weekly tab, or in Edit Timesheet Entry.


Q: Does timesheet labor sync to QuickBooks?

A: No. Timesheets don't sync to QuickBooks Online. Enter labor in QuickBooks or your payroll system yourself. Don't also enter the same labor as an expense in Structur, or it will be counted twice in the Budget.


Q: Can I put one entry on two cost codes?

A: Each entry takes one cost code. To split a day, add a second line for the same day on the Weekly tab, or add a separate Daily entry for each code. See Add Time Manually.


āš ļø Common Mistakes to Avoid

āŒ Don't

āœ… Do

Pick the first matching code from your custom codes

Pick the line from the Budget so labor lands on its proposal or change order

Click Confirm on the warning without reading it

Use Back to selection and choose a Budget line unless the work is truly outside the contract

Leave entries without a cost code

Give every entry a Budget line so it doesn't pile up in Uncategorized

Log the same crew time as a timesheet and an expense

Use Timesheets for crew time and keep it out of Expenses

Read the labor column as hours

Read it as labor cost in dollars