đ Overview
Every estimate starts with quantities, and quantities start with the drawings. Measuring by hand with a scale ruler is slow. Counting fixtures on a printed sheet is easy to get wrong. And when the numbers live on a marked-up printout or a separate spreadsheet, nobody else on the team can check how you got them.
Takeoff lets you measure right on your drawings inside Structur. You create a takeoff package on a lead or project, add your plan sheets, set the scale, and measure lengths, areas, counts and angles with on-screen tools. Measurements are sorted into groups, such as walls, flooring or doors, and they save as you go.
Each package has a status, so your team can see which takeoffs are still drafts, which are in progress and which are complete. When your quantities are ready, you can send them on to an estimate.
đ Understanding Takeoff
⥠What It Does
Takeoff allows you and your team to:
Create takeoff packages on any lead or project -- one per building, phase or trade if you need
Add plan sheets from your computer or from Project Files, with each page of a PDF becoming its own sheet
Set the scale for each sheet by calibrating against a known dimension or choosing a preset scale
Measure lengths, areas, counts and angles with eight tools on the canvas
Organize measurements into groups that you can name, hide and sort
Track progress with the Draft, In Progress and Complete statuses
See every package on a lead or project, or across All Projects
Control access with a Takeoff permission for each role
đ When to Use It
Takeoff is most valuable when you want to:
Measure quantities from a plan set without printing it
Count fixtures, doors or outlets across several sheets
Keep your measurements where the rest of the team can review them
Split a big job into separate packages by building, phase or trade
See at a glance which takeoffs still need doing
đ Step-by-Step Instructions
1. Open Takeoff
Open a lead or project
Click Takeoff in the module bar along the top (under Preconstruction)
The top of the page has Export and New Takeoff Package.
Note: If you don't see Takeoff in the module bar, it may be hidden. Use Show/Hide Features at the right end of the bar to turn it back on.
2. Create a Takeoff Package
Click New Takeoff Package
In Create New Takeoff Package, enter a Name, for example "Smith Kitchen Remodel Main Floor". The name is required.
Click Create Takeoff Package
You'll see "Takeoff package created", and the package opens. A new package starts with Draft status. The package header has Mark as Complete and Send to Estimate. Packages work the same way on a lead as on a project.
3. Add Sheets
At the bottom of the Sheets card on the left, click + New Sheet
In the Add New Sheet window, choose a tab:
Upload From Computer -- click browse or drag a file into the box
Select From Project Files -- click a folder to open it, then pick one file
Click Add Sheet
When you upload from your computer, the file shows with its type, name and size and a progress percentage, and a Preview appears once it reaches 100%. After you click Add Sheet, you'll see "1 sheet added successfully", and the canvas shows Set Scale until you set the sheet's scale.
A multi-page PDF is split into one sheet per page. A 10-page PDF takes a few seconds, and a large plan set takes longer.
The upload tab lists the accepted file types: documents such as PDF, images such as PNG, JPG and HEIC, CAD/BIM files such as DWG, and archives such as ZIP. The limit is 50MB per file, or 250MB for CAD/BIM files.
The Sheets card shows how many sheets the package has and how many measurements are on each one. Use Search sheets to find a sheet by name. The three-dot menu sorts the list by Sheet code, Title or Measurement count, and switches between List and Thumbnails view.
Note: A file uploaded from your computer becomes a sheet named after the file, for example "Plans.png". A sheet added from Project Files that doesn't get a sheet number and title is named after the file and page, for example "Plans.pdf - Page 1". Sheets can't be renamed, so give files clear names before you add them.
To delete a sheet, hover over it, click the trash icon, then click Delete.
Important: Deleting a sheet also removes the groups and measurements tied to that sheet. This can't be undone, so check the sheet's measurement count before you delete it.
4. Find Your Way Around a Package
The package page has three cards: Sheets on the left, the drawing canvas in the centre, and Groups on the right. Click the arrow on either side card to collapse it to a slim strip and give the drawing more room. Click it again to expand it.
The header shows a back arrow, the lead or project name and the package name, Mark as Complete and Send to Estimate.
Click a sheet to open it on the canvas. The controls in the top right of the canvas are Zoom Out, Zoom In, Fit to View and Rotate 90°. Rotating turns the sheet and its measurements together and doesn't change any values.
Note: Rotation isn't saved. The sheet goes back to its normal orientation when you reload the page.
5. Set the Scale
Set the scale on each sheet before you measure. Until you do, the top-left of the canvas shows Set Scale.
Open the sheet and click Set Scale. The Calibrate Scale drawer opens.
Choose the Unit System: Imperial or Metric
Choose the Precision, for example 1/16". For Metric, also choose the Display Units.
Choose the Page Range: Current Page or All Pages (the default)
Click Start Calibration
Click two points on the drawing at either end of a dimension you know, such as a dimensioned wall
Enter the real length under Calibration Length (Feet and Inches for Imperial)
Click Set Scale
The canvas now shows the scale, for example Scale: 1/4" = 1'-0", with Calibrate next to it.
Note: Page Range only covers sheets already in the package. Sheets you add later show Set Scale again, so set the scale on them before measuring.
6. Use a Preset Scale
Once a sheet has a scale, you can switch it to a standard scale from the drawing's title block.
Click the ruler icon to the left of Scale: (its tooltip reads Preset Scales)
Search or scroll the list and pick a scale
The list covers architectural scales from 1/32" = 1'-0" to 3" = 1'-0" (including 3/16" = 1'-0"), engineering scales from 1" = 10' to 1" = 100', yard scales, metric scales from 1:2 to 1:1000, and 1/1 (1:1).
Note: Currently, changing a sheet's scale doesn't update measurements you've already drawn on it. They keep the old scale, so one sheet can end up with a mix. Set the scale before you start measuring. If you change it later, delete and redraw the earlier measurements.
7. Create Groups
Groups keep your measurements organized, for example by trade or by cost code.
At the bottom of the Groups card on the right, click + New Group
Type a name in New group name and press Enter
Each group row has an eye icon to hide or show the group on the plan, and a three-dot menu with Rename and Delete.
The three-dot menu at the top of the Groups card sorts groups by Manual order, Name, Measurement count or Unit. It also has Expand all, Collapse all, Show all on plan and Hide all on plan. Use Search groups to find a group.
Note: Currently, hiding a group hides its lines and outlines, but its value labels, count dots and angle marks stay on the plan.
Important: Deleting a group also removes every measurement in it. This can't be undone, so check the group is empty or no longer needed first.
8. Measure
Click a group in the Groups card. The canvas shows Measuring for and the group's name.
Choose a tool from the toolbar at the bottom of the canvas
Draw the measurement (see below for how to finish each shape)
The measurement saves to the selected group and appears in its list. Click the group again to deselect it.
Note: You can measure with no group selected. The measurement is saved ungrouped and listed below your groups. Select the group first, because there's currently no option to move a measurement into a different group.
The eight tools, and how to finish each one:
Select -- select a measurement on the plan. Click it when you're done measuring.
Line -- click the start point, then double-click the end point
Rectangle -- click one corner, then click the opposite corner
Polygon -- click each corner, then double-click the start point to close and save the area
Path -- click each point along the run, then double-click the last point
Count -- click each item to drop a dot, then click the Select tool to save the count
Bezier Curve -- click points to draw an arc through them
Compass -- click, click, then double-click to measure an angle
Note: Currently, a single click on a polygon's start point closes the shape and shows the area, but doesn't save it. Double-click the start point to save it.
Note: Currently, a count isn't saved until you switch tools. Don't press Enter to finish a count, because it clears the dots. The group shows the result as count points on the plan, for example "5 count points on plan".
Note: Currently, Bezier Curve measurements may not save. If one doesn't appear in the group list, use Path with several points along the curve.
Measurements save as you finish them. There's no Save button.
9. Rename or Delete a Measurement
Measurements are named by type, such as Length_1, Rectangle_1, Area_1 (polygons), Path_1, Angle_1 and Count_1.
To rename one, hover over it in the Groups card, click the pencil icon, type the new name and press Enter.
To delete one, hover over it, click the X, then click Delete.
10. Track Status and Mark as Complete
Every package has a status: Draft, In Progress or Complete. Status doesn't change on its own. Adding sheets and measurements leaves a package at Draft until you change it.
To change the status, click the status pill on the package's row in the list and pick Draft, In Progress or Complete. The change saves straight away.
To complete a package, click Mark as Complete in the package header, or choose it from the row's three-dot menu in the list. There's no confirmation. The package moves to Complete, and Mark as Complete leaves the row's menu.
A completed package can still be edited, measured and added to. To reopen it, click its status pill and choose In Progress.
When you're ready to price the work, click Send to Estimate in the package header. It opens the Inventory panel, where you add cost codes and unit costs and send your measurements to a Draft estimate.
11. Work With the Takeoff List
The cards at the top of the list are Draft, In Progress and Complete, each with how many packages are in that status. The tabs All, Draft, In Progress and Complete filter the list. The list shows Title, Status, Updated By and Updated, with the most recently changed package first.
Click Open on a row to open the package
Type in Search... to find a package, or switch between List and Grid
The three-dot menu on a row has Mark as Complete (until the package is complete), Edit and Delete. To rename a package, choose Edit, change the Name and click Save Changes
Export has Export PDF and Export CSV
Note: Currently, the Sheets and Measured figures on Grid cards don't match what's in the package. For example, a package with one sheet can show 17. Open the package to see its real sheet count and measurements.
In the All Projects view of Takeoff, click the filter icon and turn on Include completed projects to see packages on completed jobs. It's off by default.
12. Delete a Takeoff Package
In the list, click the three-dot menu on the package's row
Choose Delete
Click Delete in the Delete Takeoff Package window
The window reads: "Are you sure you want to delete the "<name>"? All associated data and measurements within this package will be permanently removed. This action cannot be undone." You'll see "Takeoff package deleted successfully", and the row is removed from the list.
Important: Check you no longer need the package before you delete it.
Note: Currently, if you choose Delete from a card in Grid view, the window can't be cancelled. Reload the page to close it, and delete from List view instead.
13. Control Who Can Use Takeoff
Access to Takeoff is set per role in Settings > Permissions. Choose a role, then find the Takeoff row in the Preconstruction section. The levels are:
Access Denied -- no access to Takeoff
View Only -- can view but not make changes
Collaborate -- can create and edit, but not delete or manage settings
Full Access -- full control, including delete and settings
Note: Permissions apply company-wide to everyone with that role.
â Best Practices
Set the scale before you measure -- changing it later leaves earlier measurements at the old scale, so your quantities won't add up.
Check a known dimension after calibrating -- draw a line over a dimension printed on the sheet. If it doesn't match, recalibrate before going further.
Calibrate on the longest dimension you can find -- a small error over a short line becomes a big error across a whole floor plan.
Select a group before you measure -- measurements can't be moved between groups afterwards, so an ungrouped measurement has to be redrawn.
Rename measurements as you go -- names like "North Wall" are easier to check than Length_1 to Length_20, and default names can repeat between groups.
Use one package per building, phase or trade -- smaller packages are easier to review and complete.
Update the status yourself -- Takeoff doesn't move a package out of Draft for you, so the counts at the top of the list are only as current as your statuses.
â Common Questions
Q: How do I save my takeoff?
A: Each measurement saves as soon as you finish it, and stays after you reload the page. There's no Save button. The exception is a count, which saves when you switch to another tool.
Q: Do I have to create a group before I measure?
A: No. Without a group selected, the measurement is saved ungrouped and listed below your groups. Currently, there's no option to move it into a group later, so select the group first or delete and redraw it.
Q: My quantities look wrong. What should I check?
A: Check the scale shown on the canvas for that sheet. Draw a line over a dimension printed on the drawing and compare. If the scale was changed after you measured, the earlier measurements still use the old scale, so delete and redraw them.
Q: The scale I need isn't in Preset Scales.
A: Use Calibrate instead. Click two points on a known dimension and enter its real length. 3/16" = 1'-0" is in the list, so search for it if you're looking for that one.
Q: Why didn't my package move to In Progress when I started measuring?
A: Status is set by hand. Click the status pill in the list and choose In Progress, or click Mark as Complete when you're done.
Q: Can I still change a completed takeoff?
A: Yes. A completed package can still be measured and edited. To show it as active again, click its status pill and choose In Progress.
Q: Can I save a set of groups as a template?
A: Currently, no. Groups are created in each package. Use the same group names across packages so they're easy to compare.
Q: The drawing is stuck loading. What can I do?
A: Reload the page. If it's still loading, reload it once more.
Q: What's the difference between Takeoff and Bid Packages?
A: Takeoff is for measuring quantities from your drawings. Bid Packages are for sending scope to subcontractors and collecting their prices.
â ď¸ Common Mistakes to Avoid
â Don't | â Do |
Start measuring before setting the sheet's scale | Calibrate or pick a preset scale on every sheet first, including sheets added later |
Change the scale after measuring and trust the old numbers | Delete and redraw measurements made before the change |
Measure without a group selected | Click the group first so the measurement lands in the right place |
Press Enter to finish a count | Click the Select tool to save the count |
Single-click a polygon's start point and move on | Double-click the start point so the area saves |
Delete a sheet or group without checking what's on it | Check the measurement count first, because its measurements are removed too |
Expect the status to update itself | Set In Progress and Mark as Complete yourself |