Compare and Award Bids

Covers reviewing each vendor's bid on the Bids tab, the Low, High and Avg figures, comparing bids side by side on Leveling, awarding a bid, what vendors see and receive, and pushing the awarded bid to an estimate or converting it to a subcontract.

Written by Support

šŸ“‹ Overview

The lowest total isn't always the best bid. One sub leaves out a line, another prices labor high and materials low. Comparing bids that arrive as emails and attachments means retyping them into a spreadsheet, and that's where mistakes get made.

In Structur, every bid comes back into the package line by line. You see each vendor's bid on its own, then all of them side by side, and award the winner in a couple of clicks. From there you can push the winning lines to your estimate or turn the bid into a subcontract.


šŸ” Understanding Bid Review

⚔ What It Does

Comparing and awarding bids allows you and your team to:

  • Review each bid -- every line and the total

  • See the spread at a glance -- Low, High and Avg in the header

  • Compare bids side by side -- with the lowest price on each line highlighted

  • Award the winner -- the winning vendor gets an email

  • Use the awarded bid -- push it to an estimate or convert it to a subcontract

šŸ“… When to Use It

This is most valuable when you want to:

  • Spot a bid that skipped or underpriced a line

  • Pick a winner on more than the total

  • Build your estimate from real sub prices

  • Turn the winning bid into a subcontract without retyping it


šŸ“ Step-by-Step Instructions

1. Review Each Bid

  1. Open the bid package and click the Bids tab

  2. Pick a vendor in the list on the left

The vendor list shows each vendor's status and the date they submitted. The bid shows COST CODE, NAME, DESCRIPTION and BID AMOUNT for every line, the Bid Total, and your Company note (the scope).

Until a vendor bids, the tab says "No bids yet".

The header keeps a running summary: Submitted (for example 2/2), and the Low, High and Avg bid totals.


2. Compare Bids Side by Side

  1. Click the Leveling tab

Bid Leveling shows every submitted bid side by side, one column per vendor, with each vendor's total at the bottom. The lowest price on each line, and the lowest total, are shown in green.

Tip: A vendor can have the lowest total and still be high on some lines. Use Leveling to see where the prices really differ.


3. Award a Bid

  1. On the Bids tab, pick the winning vendor

  2. Click Award Bid

  3. Read the window: "This will award the [package] bid package to [vendor]." It shows the bid total.

  4. Click Confirm Award

You'll see "Bid awarded successfully". The package changes to Awarded, the winner shows Won and the other vendors show Lost. Edit and Duplicate leave the header.

The winning vendor gets an email saying you've awarded them the bid request, with a button to view it. The other vendors aren't emailed, so let them know yourself.

Vendors' bid pages become read-only once you award.


4. Push the Awarded Bid to an Estimate

After the award, the Bids tab shows Push Awarded Bid to Estimate. It adds the awarded line items and amounts to an estimate on the job.

  1. Click Push to Estimate

  2. Pick an Estimate from Select a draft estimate...

  3. Under Destination, choose Create a new group (named after the package unless you change New Group Name), Add to an existing group, or No group (individual line items)

  4. Confirm at the bottom of the window

Note: You can only push to a draft estimate. If the job has none, the button at the bottom reads No estimate found. Create a draft estimate first.


5. Convert the Awarded Bid to a Subcontract

Convert Awarded Bid to Subcontract creates a subcontract for the winning vendor using the awarded line items and amounts.

  1. Click Convert to Subcontract

  2. Click Convert to Subcontract again to confirm


6. Check the Activity Log

The Activity tab lists what happened on the package and when, such as when it was created, when lines were added and each time it was sent to a vendor.


⭐ Best Practices

  • Wait for the bids you need -- the header's Submitted count shows who's still out.

  • Read Leveling, not just the totals -- a low total can hide a missing or underpriced line.

  • Tell the other vendors -- only the winner is emailed.

  • Have a draft estimate ready -- Push to Estimate needs one.


ā“ Common Questions

Q: Do the vendors who lost get told?

A: No. Only the winning vendor gets an email. Let the others know yourself.


Q: Can I change a package after awarding it?

A: Edit and Duplicate aren't available once a package is awarded. Save As Template still is.


Q: Why does Push to Estimate say "No estimate found"?

A: The job has no draft estimate. Create one, then push the awarded bid to it.


Q: Can a vendor change their bid after I award it?

A: No. Vendors' bid pages are read-only once the package is awarded.


āš ļø Common Mistakes to Avoid

āŒ Don't

āœ… Do

Award on the total alone

Check Leveling line by line

Assume losing vendors were told

Let them know yourself

Retype the winning bid into your estimate

Use Push to Estimate

Push before you have a draft estimate

Create the draft estimate first